Generates a new sprint plan or updates an existing one based on the current milestone, completed work, and team capacity. Pulls context from production docs and the story backlog. Run at sprint start, sprint mid-correction, or after a milestone shift.

35 other projects use a version of this.

Adopted by

Most recently taken up by

Used with

Projects with it also use team-combat, team-ui and 2 more.

Other files people use alongside this one.

Files found in the same public projects as a version of this one, more often than they turn up anywhere else. Each project counts once, large collections count for less, and this file's own repository is left out.
  • CoralGameSkill

    team-combat

    Orchestrate the combat team: coordinates game-designer, gameplay-programmer, ai-programmer, technical-artist, sound-designer, and qa-tester to design, implement, and validate a combat feature end-to-end.

    Also in 5 projects that use this

  • CoralGameSkill

    team-ui

    Orchestrate the UI team: coordinates ux-designer, ui-programmer, and art-director to design, implement, and polish a user interface feature from wireframe to final.

    Also in 5 projects that use this

  • +2 more from CoralGame

The file

We split this skill into the rules it gives an agent

6 rules. 0 are common, 3 are distinctive, and 3 are very specific to this project.

  • 0

    Common

    Most of the 34 edited versions we read keep these.

  • 3

    Distinctive

    This author's own choices. Worth a look.

  • 3

    Very specific

    Tied to their project's names, files or tools. Probably skip.

  • Common
  • Distinctive
  • Very specific
  1. Very specific:

    If argument is new, create a new sprint.

    line 43
  2. Distinctive:

    If a previous sprint exists, read it.

    line 65
  3. Very specific:

    Ask: "Approve and write to production/sprints/sprint-NNN-<slug>.md?"

    line 174
  4. Very specific:

    If argument is update, read the latest active sprint and:

    line 205
  5. Distinctive:

    Ask what is changing:

    line 207
  6. Distinctive:

    If a story is being removed mid-sprint, ask whether it carries to next sprint or is killed.

    line 216

“Common” is measured: kept by at least 6 in 10 of the 34 edited versions of this file we could read. “Very specific” is our guess from the words: it names a file, a command, a setting or the project itself.

Keep what fits and drop the rest. Your version, ready for your agents.
Files
SKILL.md

Sprint Plan

Builds the bridge between epic story backlogs and what gets worked on in the next 1-2 weeks. Decides which stories enter the sprint, who owns them (when team info is known), and what the sprint's outcome target is.

Output: production/sprints/sprint-NNN-<slug>.md


Purpose / When to Run

Run when:

  • The previous sprint just ended
  • A new epic is ready to be tackled
  • A milestone shift requires re-planning
  • The team wants to update an in-flight sprint (update mode)

Inputs

  • All epics: production/epics/*/EPIC.md
  • All stories: production/epics/*/story-*.md
  • Existing sprints: production/sprints/*.md
  • Optional production/milestones/*.md
  • design/concept.md for primary metric context
  • production/session-state/active.md

Outputs

  • production/sprints/sprint-NNN-<slug>.md

Phase 1: Mode

If argument is new, create a new sprint. If update, edit the most recent in-flight sprint. If empty, ask:

  • Prompt: "New sprint or update existing?"
  • Options: New sprint, Update existing, Show me current sprint first

For Show me current sprint first: dispatch to /sprint-status and exit.


Phase 2: Inventory Backlog & Capacity

2a: Story inventory

Glob production/epics/*/story-*.md and bucket by Status:

  • Ready
  • In Progress
  • Blocked
  • Complete

Print counts.

2b: Last-sprint signals

If a previous sprint exists, read it. Capture:

  • Stories planned vs. completed
  • Velocity (stories or rough hours)
  • Carry-over

2c: Capacity

Use AskUserQuestion:

  • Prompt: "How many engineering days are available for this sprint?"
  • Options: 5 (1-week sprint, 1 dev), 10, 15, 20, Custom (free text)

Convert to a rough story budget (e.g., 1 day = 1-2 stories of typical size). The user can override.

Use AskUserQuestion:

  • Prompt: "How many designers / QA / data days available?"
  • Options: Solo dev (none), Designer + QA shared, Full team, Free text

This affects which story types can be parallelized.


Phase 3: Pick Sprint Goal

Sprint goals must be a single sentence the team can rally around. Examples:

  • "Ship the OAuth login flow end to end."
  • "Make the Home screen feel responsive — no skeleton longer than 300ms."

Use AskUserQuestion:

  • Prompt: "Which is the sprint's primary goal?"
  • Options: derived from epics with the most Ready stories. If unclear, free text.

Phase 4: Select Stories

Walk through Ready stories, prioritized by:

  1. Foundation epics first
  2. Critical path to the sprint goal
  3. Stories that unblock multiple downstream stories
  4. Stories not blocked by Proposed ADRs

For each candidate, present:

  • Story slug + title
  • Type
  • Estimated effort (from /estimate if run, else rough)
  • Dependencies on other Ready stories

User picks; capture into the plan.

Cap selection at the story budget. If the user wants more, surface scope creep:

"Selected <N> stories — that exceeds your <M>-story budget by <X>. Want to remove some, or accept the over-commit?"


Phase 5: Write the Plan

# Sprint <NNN>: <slug>

> **Status**: Active
> **Start**: <date>
> **End**: <target date>
> **Capacity**: <days>
> **Manifest Version**: <date from control-manifest>

## Goal
<one sentence>

## Success Looks Like
- <observable end-of-sprint outcomes — e.g., "User can sign in with Apple and Google", "Crash-free rate ≥ 99.5% on internal builds">

## Sprint Backlog

| Story | Title | Epic | Type | Owner | Status |
|-------|-------|------|------|-------|--------|
| 001 | OAuth network call | auth-sign-in | Logic | <name or unassigned> | Ready |
| ... | | | | | |

## Out of Scope (carry to next sprint)
- <list — stories considered but not selected>

## Risks
- <list — engineering or external risks that could derail>

## Dependencies on Other Tracks
- Design: <list>
- Backend / API: <list>
- QA: <list>

## Daily Rhythm
- Standup: <time> (or "async via <channel>")
- Sprint review: <date>
- Retrospective: <date>

## Definition of Sprint Done
- [ ] All Sprint Backlog stories at Status: Complete
- [ ] Smoke check passes (`/smoke-check` in second skill set)
- [ ] No new control-manifest violations introduced
- [ ] Sprint demo deck (or video) prepared
- [ ] Retrospective scheduled

## Metrics to Watch
<from concept.md primary metric — note current baseline if known>

## Notes
- Review mode for the sprint: <full / lean / solo>
- Special calendar items: <holidays, on-call rotations>

Ask: "Approve and write to production/sprints/sprint-NNN-<slug>.md?"


Phase 6: Update Story Headers

For each story selected, update its Status: Ready to Status: In Sprint <NNN> (or simply leave as Ready and let the sprint plan be the source of truth — pick one convention and stick with it).

Recommended: keep Story Status reflecting development progress (Ready / In Progress / Blocked / Complete) and let the sprint plan be the assignment doc. Engineers move Story Status as they work; the sprint plan stays static for the period.


Phase 7: Update Active State & Hand Off

Update production/session-state/active.md:

  • Active sprint: sprint-NNN-<slug>
  • Sprint goal: <goal>
  • Top story to start: <story-001>

Print:

"Sprint plan written. Engineers can pick stories with /story-readiness <path> then /dev-story <path>. Run /sprint-status any time for a snapshot."

Use AskUserQuestion:

  • Run /story-readiness for the first story
  • Run /scope-check on this sprint
  • Stop here

Update Mode

If argument is update, read the latest active sprint and:

  1. Show current state (stories by status, days remaining, burndown estimate)
  2. Ask what is changing:
    • Add stories (scope expansion)
    • Remove stories (scope reduction)
    • Reassign owners
    • Move dates
    • Update sprint goal
  3. Apply changes via Edit
  4. Append a ## Mid-Sprint Update <date> section recording what changed and why — never silently overwrite

If a story is being removed mid-sprint, ask whether it carries to next sprint or is killed.


Quality Gates

  • Sprint goal is one sentence, not a paragraph
  • Success Looks Like is observable (not "improve quality")
  • Backlog count fits within capacity, or over-commit is explicit
  • Manifest Version is recorded
  • Risks section is non-empty (a sprint without surfaced risks is unrealistic)

Examples

/sprint-plan new

  • Capacity: 10 dev-days, 1 designer half-time, 1 QA half-time
  • Goal: "Ship sign-in end to end."
  • Backlog: 8 stories from auth-sign-in epic (5 Logic, 2 UI, 1 Platform)
  • Out of scope: account-recovery (next sprint)
  • Risks: ADR-0007 (biometric) still Proposed; sign-in story 005 is Blocked until that lands

/sprint-plan update

  • Adds 1 story (paywall copy quick-design)
  • Removes 1 story (push token registration — pushed to next sprint)
  • Logs change rationale in ## Mid-Sprint Update

Download now (ZIP)

Does it work?

Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.

No reviews yet

People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.

  • It worked
  • Partly
  • It didn't
What did you use it for? e.g. Reviewing pull requests in a Rails app

Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.

Your trail

Files you open will collect here, so you can find them again.

Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.

Now do this for your own.

Bring your CLAUDE.md, AGENTS.md or skills. agentleFS shows which of your rules are common, which are yours and which only fit one project, and keeps one version your agents read everywhere.