neqsim-equipment-cost-estimation
Skill167 starsChanged 7 months agoApache-2.0View on GitHub
Equipment and process CAPEX estimation - Turton/Peters/Seider correlations, CEPCI escalation, material/pressure factors, bare-module to grass-roots, AACE class 1-5, location and currency factors, mechanical-design-driven topsides/SURF/well rollups. USE WHEN: a task needs a Class 3/4 estimate for equipment, a flowsheet, topsides, SURF, wells or reservoir-to-market CAPEX. Anchors on CostEstimationCalculator and ProcessCostEstimate.
In this repository140 other files it gives its agents.
- AGENTS.mdAGENTS.md
- CLAUDE.mdCLAUDE.md
- .github/copilot-instructions.mdCopilot instructions
- analyze-convergenceSkill
- analyze-gibbs-convergenceSkill
- book-creationSkill
- design-flash-benchmarkSkill
- design-reactor-benchmarkSkill
- figure-discussionSkill
- generate-publication-figuresSkill
- journal-formattingSkill
- neqsim-acid-gas-treatingSkill
- neqsim-advanced-control-mpc-and-virtual-sensingSkill
- neqsim-agent-handoffSkill
- neqsim-agentic-process-optimizationSkill
- neqsim-api-patternsSkill
- neqsim-autonomous-investigationSkill
- neqsim-capability-mapSkill
- neqsim-capacity-and-utilization-analysisSkill
- neqsim-capacity-increase-screeningSkill
- neqsim-ccs-hydrogenSkill
- neqsim-code-healthSkill
- neqsim-code-hygieneSkill
- neqsim-code-reviewSkill
- neqsim-column-internals-and-rate-basedSkill
- neqsim-compressor-antisurge-recycleSkill
- neqsim-consequence-analysisSkill
- neqsim-continuous-task-improvementSkill
- neqsim-controllability-operabilitySkill
- neqsim-cooling-waterSkill
- neqsim-cpa-water-boundariesSkill
- neqsim-depressurization-mdmtSkill
- neqsim-distillation-designSkill
- neqsim-document-intelligence-extractionSkill
- neqsim-dynamic-equipment-implementationSkill
- neqsim-dynamic-simulationSkill
- neqsim-electrolyte-systemsSkill
- neqsim-emulsion-separationSkill
- neqsim-energy-systems-and-electrificationSkill
- neqsim-engineering-design-packageSkill
- neqsim-eos-regressionSkill
- neqsim-exploration-strategy-selectionSkill
- neqsim-field-developmentSkill
- neqsim-field-economicsSkill
- neqsim-firewater-deluge-designSkill
- neqsim-flow-accelerated-corrosionSkill
- neqsim-flow-assuranceSkill
- neqsim-flow-assurance-study-reportSkill
- neqsim-forward-separator-trainSkill
- neqsim-future-operation-studySkill
- neqsim-hazid-fmea-eta-ftaSkill
- neqsim-heat-integrationSkill
- neqsim-hydrogen-productionSkill
- neqsim-input-validationSkill
- neqsim-integrated-production-and-lifecycleSkill
- neqsim-in-writingSkill
- neqsim-java8-rulesSkill
- neqsim-jurisdiction-regulatory-basisSkill
- neqsim-literature-searchSkill
- neqsim-lng-liquefactionSkill
- The first 60 shown.
The file
We split this skill into the rules it gives an agent
3 rules. About 0 are common, 1 is distinctive, and 2 are very specific to this project.
≈0
Common · estimate
Many files like this have a rule of this kind.
≈1
Distinctive · estimate
This author's own choices. Worth a look.
2
Very specific
Tied to their project's names, files or tools. Probably skip.
- Common
- Distinctive
- Very specific
- Very specific: line 114
Keep the legacy calcVerticalVesselCost(weight_kg) and calcHorizontalVesselCost(weight_kg) methods for cases where the mechanical design has …
- Distinctive: line 193
Use this rollup for reservoir-to-market screening once the flowsheet contains unit operations for the major equipment.
- Very specific: line 200
Use CostEstimateResult when handing estimates to reports, agents, or downstream economics.
≈ “Common” is an estimate: at least 1 in 5 of the 350,495 skill files we read have a rule of the same kind, not the same words. “Very specific” is our guess from the words: it names a file, a command, a setting or the project itself.
Files
NeqSim Equipment Cost Estimation Skill
Class-3/4 (AACE 18R-97) order-of-magnitude to study estimates for individual
process equipment and early process/facility CAPEX rollups - the bridge between
sized equipment and a project economics model. Wraps Turton (5e),
Peters–Timmerhaus, Ulrich, and Seider correlations with CEPCI escalation,
material factors, pressure factors, and Lang/Hand factors.
The preferred NeqSim path is mechanical-design driven: call each unit's
initMechanicalDesign(), calcDesign(), then
getMechanicalDesign().getCostEstimate().calculateCostEstimate() or let
ProcessCostEstimate.calculateAllCosts() do that rollup for a full flowsheet.
When to Use
- Quickly cost a sized vessel, column, HX, pump, compressor, filter, reactor, mixer, splitter, or manifold
- Build a bare-module → total-module → grass-roots stackup
- Apply CEPCI to escalate published correlations to current year
- Compare alternatives (e.g. centrifugal vs reciprocating compressor)
- Produce a scope-safe
CostEstimateResultfor equipment, process, topsides, SURF, subsea, well, or field-development estimates - Reconcile located process totals against located equipment rows while retaining base equipment costs
- Feed equipment cost into NPV / IRR via
neqsim-field-economics
For project-level economics, asset valuation, or fiscal regimes, use
neqsim-field-economics. This skill is the CAPEX basis skill that feeds those economics workflows.
AACE Cost Estimate Classes
| Class | Maturity | Accuracy | Method |
| 5 | Concept | −50% / +100% | Capacity-factor (six-tenths) |
| 4 | Pre-FEED | −30% / +50% | Equipment-factored (this skill) |
| 3 | FEED | −20% / +30% | Sized equipment + bulk MTOs |
| 2 | Detailed | −15% / +20% | Detailed quantity takeoff |
| 1 | Final | −10% / +15% | Vendor quotes |
Correlation Validity Range (READ THIS FIRST)
The Turton correlations are fitted over a stated capacity range. NeqSim does not refuse a capacity outside that range — it evaluates the polynomial anyway and returns a number that looks ordinary.
Observed case: a 239 MW compression duty evaluated against a correlation valid to 3000 kW
returned about 6 MUSD — roughly 80× too low, with no warning. In the same study the
weight-based calcColumnShellCost returned ~500 MUSD for a single contactor because it feeds a
shell weight into coefficients fitted on volume. The two errors partly cancelled, and the
study total was wrong by a factor of three while appearing internally consistent.
Rules:
- Check the range before calling. Compressors 450–3000 kW; pumps 1–300 kW; vessels by volume.
- Oversized duties are parallel units, not extrapolation. Split the duty into
ceil(capacity / max_capacity)units atcapacity / neach and cost each inside the range.CostEstimationCalculatornow does this internally for compressors and pumps. - Never use the weight-based vessel/column methods.
calcVerticalVesselCost,calcHorizontalVesselCostandcalcColumnShellCostare deprecated: their capacity basis is volume, not shell weight. UsecalcVerticalVesselCostByVolumeand pass the actual volume. - Anchor the total. Cross-check specific CAPEX against a published comparable for the concept type before believing the sum. A result outside the expected band by more than a factor of 1.5 is a bug until proven otherwise.
Pattern 1 — Bare-module Cost for a Vessel
import neqsim.process.costestimation.CostEstimationCalculator;
CostEstimationCalculator cost = new CostEstimationCalculator();
cost.setCurrentCepci(CostEstimationCalculator.CEPCI_2025); // 840
cost.setMaterialOfConstruction("SS316"); // sets Fm = 2.1
cost.setLocationByRegion("Norway"); // location factor
double shellWeight_kg = 8500.0; // from mechanical design
double designP_barg = 110.0;
double Cp = cost.calcVerticalVesselCost(shellWeight_kg);
double Cbm = cost.calcBareModuleCost(Cp, designP_barg); // applies Fp & Fm
double Ctm = cost.calcTotalModuleCost(Cbm); // + contingency + fees
double Cgr = cost.calcGrassRootsCost(Ctm); // + auxiliary facilitiesPattern 2 — End-to-end via calculateCostEstimate
cost.calculateCostEstimate(
Cp, // purchased equipment cost
designP_barg, // for Fp
shellWeight_kg, // for installation man-hours
"vertical_vessel" // equipment category
);
String json = cost.toJson(); // structured output for results.jsonPattern 3 — Volume-Based Vessel Cost
For screening work, use the volume-based methods when the mechanical design knows vessel diameter and length but the shell weight is not yet reliable. These are now the preferred basis for separator, absorber, column, filter, and reactor vessel screening.
double vesselVolume_m3 = Math.PI * diameter_m * diameter_m / 4.0 * tanTanLength_m;
double verticalCp = cost.calcVerticalVesselCostByVolume(vesselVolume_m3);
double horizontalCp = cost.calcHorizontalVesselCostByVolume(vesselVolume_m3);Keep the legacy calcVerticalVesselCost(weight_kg) and
calcHorizontalVesselCost(weight_kg) methods for cases where the mechanical
design has already produced a defensible shell weight.
Pattern 4 — CEPCI Escalation
C_today = C_published × CEPCI_today / CEPCI_publishedBuilt-in indices: CEPCI_2019 (607.5) through CEPCI_2025 (840). Escalate any
literature correlation that's published with a base year.
Pattern 5 — Equipment-Specific Methods
| Equipment | Method | Sizing input |
| Vertical pressure vessel | calcVerticalVesselCost(weight_kg) | shell weight |
| Horizontal vessel | calcHorizontalVesselCost(weight_kg) | shell weight |
| Vertical vessel screening | calcVerticalVesselCostByVolume(volume_m3) | vessel volume |
| Horizontal vessel screening | calcHorizontalVesselCostByVolume(volume_m3) | vessel volume |
| Distillation column | calcColumnShellCost(weight_kg) + calcSieveTraysCost(D, N) | weight + diameter + tray count |
| Shell-tube HX | calcShellTubeHeatExchangerCost(area_m2) | area |
| Plate HX | calcPlateHeatExchangerCost(area_m2) | area |
| Air cooler | calcAirCoolerCost(area_m2) | bare-tube area |
| Centrifugal pump | calcCentrifugalPumpCost(power_kW) | shaft power |
| Centrifugal compressor | calcCentrifugalCompressorCost(power_kW) | shaft power |
| Reciprocating compressor | calcReciprocatingCompressorCost(power_kW) | shaft power |
| Piping | calcPipingCost(D_m, L_m, schedule) | diameter, length |
| Control valve | calcControlValveCost(Cv) | Cv |
Pattern 6 — Mechanical-Design Estimator Wiring
Equipment-specific mechanical designs own their estimator selection. This is
what makes full-process rollups work: ProcessCostEstimate does not need to
know every unit's detailed sizing correlation; it asks the unit for its
mechanical design and cost estimate.
unit.initMechanicalDesign();
MechanicalDesign design = unit.getMechanicalDesign();
design.calcDesign();
design.getCostEstimate().calculateCostEstimate();
double grassRootsCostUSD = design.getCostEstimate().getGrassRootsCost();Current topside coverage includes specialized mechanical-design/cost paths for
separators, scrubbers, columns, absorbers, adsorbers, mercury removal, pumps,
compressors, expanders, ejectors, heat exchangers, BAHX units, tanks, pipelines,
valves, mixers, splitters, filters, reactors, and manifolds. Header-like units
such as mixers and splitters should calculate dry weight during calcDesign();
filter/reactor/manifold estimators reuse the mechanical design outputs instead
of duplicating sizing logic.
Pattern 7 — Material and Pressure Factors (Turton)
double Fp = CostEstimationCalculator.getPressureFactor(designP_barg); // ~1.0–3.0
// Fm constants: FM_CARBON_STEEL=1.0, FM_SS304=1.8, FM_SS316=2.1,
// FM_SS316L=2.3, FM_MONEL=3.2, FM_HASTELLOY_C=3.8, FM_TITANIUM=4.5Pattern 8 — Stackup Convention
Cp = purchased equipment, FOB factory (input)
Cbm = Cp × (B1 + B2 × Fm × Fp) bare module
Ctm = Cbm × 1.18 + contingency 15% + fees 3%
Cgr = Ctm × 1.30 + 30% auxiliary (utilities, storage, OSBL)Pattern 9 — Cost Estimate for a Whole Process
ProcessCostEstimate processCost = new ProcessCostEstimate(process);
processCost.calculateAllCosts();
double totalCgr = processCost.getTotalGrassRootsCost();Use this rollup for reservoir-to-market screening once the flowsheet contains
unit operations for the major equipment. It initializes each unit's mechanical
design, runs calcDesign(), calls the attached estimator, and aggregates the
result by equipment category.
Pattern 10 — Result Schema and Reconciliation
Use CostEstimateResult when handing estimates to reports, agents, or downstream
economics. The map names encode whether rows are additive, summary totals, or
non-cost quantities:
| Map | Meaning | Reconciliation Rule |
capitalCosts_USD | Additive direct capital-cost lines | Sum only inside the same scope |
capitalCostBreakdown_USD | Supplementary detail behind a capital line | Do not add to the parent line |
capitalCostSummary_USD | Capital subtotals/totals | Show as totals; do not re-sum |
projectCosts_USD | Additive project-cost lines | Sum only inside the matching project scope |
projectCostSummary_USD | Project subtotals/totals | Show as totals; do not re-sum |
quantityBasis | Non-cost quantities with units | Never mix into USD totals |
weightBasis_kg and materialTakeOff | Physical basis and MTO traceability | Keep separate unless building a controlled MTO rollup |
Examples of intended placement:
- Unit estimators:
purchasedEquipmentCostincapitalCosts_USD;bareModuleCost,totalModuleCost, andgrassRootsCostincapitalCostSummary_USD;installationManHoursinquantityBasis. ProcessCostEstimate: process PEC/BMC/TMC/grass-roots incapitalCostSummary_USD;totalProjectCostinprojectCostSummary_USD;totalInstallationManHoursinquantityBasis.- Topsides facilities: direct field cost and excluded non-topsides scope in
capitalCostSummary_USD;totalTopsidesCapexinprojectCostSummary_USD; module detail incapitalCostBreakdown_USD. - SURF/development:
totalSURFandtotalDevelopmentincapitalCostSummary_USD; vessel days inquantityBasis.
ProcessCostEstimate.toJson() reports equipment rows with location-adjusted
costs in the standard *_USD fields, because those rows must reconcile with the
process totals and costByEquipmentType_USD. Base, unlocated rows remain under
basePurchasedEquipmentCost_USD, baseBareModuleCost_USD,
baseTotalModuleCost_USD, and baseGrassRootsCost_USD, with locationFactor
shown explicitly.
Common Mistakes
| Mistake | Fix |
| Using outdated CEPCI | Always set setCurrentCepci(CEPCI_<year>) before calculating |
| Hardcoding Fm = 1 | Pick from FM_* constants based on actual material of construction |
| Missing pressure factor at high P | Use getPressureFactor(P) — silently × the cost at HP/HIPPS service |
| Reporting Cp as "installed cost" | Cp is FOB only; installed = at minimum Cbm |
| Mixing currencies | Use setCurrency(code, rate) then read all costs through convertFromUSD/convertToUSD |
Adding capitalCostSummary_USD into capitalCosts_USD totals | Summary rows are already subtotals/totals; show them separately |
Treating quantityBasis rows as USD costs | Quantity rows carry units like man-hour or vessel-day, not currency |
| Comparing located process totals to base equipment rows | Use located *_USD equipment fields for reconciliation, base fields for pre-location analysis |
| Claiming Class-3 accuracy on capacity-factored | Capacity factor (six-tenths) → Class 5; named in AACE 18R-97 |
| Ignoring location | setLocationByRegion("Norway") ≈ 1.3× US Gulf Coast for offshore |
| Adding a new mechanical design but leaving the base estimator | Assign the unit-specific costEstimate in the mechanical design constructor |
| Passing shell weight to a volume correlation | Use calc*ByVolume(volume_m3) only with vessel volume |
SURFCostEstimator for a tie-back or infill template | It adds a default 80 km x 24 in export pipeline (about 340 MUSD) and a 10 km x 14 in infield flowline; call setExportPipelineLengthKm(0.0) and set the infield length/diameter, otherwise the SURF total is 2-3 times too high |
| Expecting PiP, SS-clad or CRA flowline items | SURFCostEstimator prices rigid carbon steel or flexible only; apply an explicit uplift or unit rate (MUSD/km) and state it as an assumption |
WellCostEstimator well-type strings | Use OIL_PRODUCER, WATER_INJECTOR, GAS_INJECTOR; rig SEMI_SUBMERSIBLE; completion ICD, AICD, OPEN_HOLE, MULTI_ZONE; a default rig day rate applies unless overridden |
Validation Checklist
- CEPCI year matches the project base year
- Material of construction set per stream service (e.g. SS316L for wet sour)
- Pressure factor applied for design P > 10 barg
- AACE class declared in report (5/4/3) with stated accuracy band
- Stackup shown: Cp → Cbm → Ctm → Cgr with each multiplier
- Currency and location factor stated
- Additive cost rows, summary totals, supplementary breakdowns, and non-cost quantities are kept in separate
CostEstimateResultmaps - Process equipment rows reconcile on the same basis as totals: located-to-located or base-to-base
- JSON saved via
cost.toJson()toresults.jsonundercapexsection - Sensitivity to ±20% on key drivers (compressor power, column trays) reported
- Full-process screens include major reservoir-to-market equipment rather than only topside separators and compressors
- New equipment classes expose a specialized mechanical design and estimator before relying on
ProcessCostEstimate
Related Skills
neqsim-field-economics— project NPV / IRR / fiscalneqsim-api-patterns—CompressorDesignFeasibilityReportincludes integrated costneqsim-standards-lookup— AACE 18R-97
Does it work?
Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.
No reviews yet
People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.
- It worked
- Partly
- It didn't
Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.
Your trail
Files you open will collect here, so you can find them again.
Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.
Now do this for your own.
Bring your CLAUDE.md, AGENTS.md or skills. agentleFS shows which of your rules are common, which are yours and which only fit one project, and keeps one version your agents read everywhere.