Educational factored CAPEX/OPEX screening that turns a bare equipment cost into a total installed CAPEX (Lang/Hand-style installation factor + contingency), an annual OPEX, and a lifecycle total cost of ownership. USE WHEN: a task needs a public, screening-level CAPEX and OPEX magnitude before detailed NeqSim CostEstimationCalculator estimating or qualified cost-engineering review.

The file

We split this skill into the rules it gives an agent

5 rules. About 0 are common, 5 are distinctive, and 0 are very specific to this project.

  • ≈0

    Common · estimate

    Many files like this have a rule of this kind.

  • ≈5

    Distinctive · estimate

    This author's own choices. Worth a look.

  • 0

    Very specific

    Tied to their project's names, files or tools. Probably skip.

  • Common
  • Distinctive
  • Very specific
  1. Distinctive:

    Use this skill for a quick, public screening of project cost.

    line 16
  2. Distinctive:

    When a user wants a first-pass CAPEX and OPEX magnitude for a concept.

    line 27
  3. Distinctive:

    When an agent needs a cost feed for an asset-value / NPV screening chain.

    line 28
  4. Distinctive:

    When examples must run without confidential cost data or licensed estimating tools.

    line 29
  5. Distinctive:

    No confidential data or proprietary methods are included.

    line 125

≈ “Common” is an estimate: at least 1 in 5 of the 350,495 skill files we read have a rule of the same kind, not the same words. “Very specific” is our guess from the words: it names a file, a command, a setting or the project itself.

Keep what fits and drop the rest. Your version, ready for your agents.
Files
SKILL.md

CAPEX/OPEX Screening

Use this skill for a quick, public screening of project cost. Given a bare equipment cost, it applies a public installation (Lang/Hand-style) factor and a contingency allowance to estimate a total installed CAPEX, then adds a simple OPEX (a fraction of CAPEX per year plus an annual energy cost) to produce a lifecycle total cost of ownership. It is intentionally simple and should guide users toward the validated NeqSim CostEstimationCalculator (Turton / Peters / Ulrich / Seider correlations with CEPCI escalation) and the NeqSim MCP runFieldEconomics workflow for real estimates.

When to Use

  • When a user wants a first-pass CAPEX and OPEX magnitude for a concept.
  • When an agent needs a cost feed for an asset-value / NPV screening chain.
  • When examples must run without confidential cost data or licensed estimating tools.

Inputs

  • bare_equipment_cost_musd: total bare (uninstalled) equipment cost in million USD.
  • installation_factor: Lang/Hand-style multiplier from bare to installed cost (default 3.5).
  • contingency_fraction: contingency added on top of installed cost (default 0.2).
  • opex_fraction_of_capex_per_year: annual OPEX as a fraction of total CAPEX (default 0.04).
  • annual_energy_use_mwh: optional annual energy use for the energy-cost term (default 0).
  • energy_price_usd_per_mwh: optional energy price (default 0).
  • project_life_years: number of years used for the lifecycle OPEX roll-up (default 20).

Outputs

  • installed_capex_musd: bare cost * installation factor.
  • total_capex_musd: installed CAPEX including contingency.
  • annual_opex_musd: OPEX-fraction term per year.
  • annual_energy_cost_musd: energy-cost term per year.
  • total_annual_opex_musd: sum of the two OPEX terms.
  • lifecycle_opex_musd: total annual OPEX times project life.
  • total_cost_of_ownership_musd: total CAPEX plus lifecycle OPEX.
  • capex_warning: ok, watch, or high (magnitude flag vs a configurable threshold).
  • neqsim_available: whether the optional NeqSim package is importable.
  • assumptions: public assumptions and required follow-up.

Engineering Method

The factored estimate uses the classic installation-factor approach: CAPEX_installed = C_equipment * f_install, then CAPEX_total = CAPEX_installed * (1 + contingency). Annual OPEX is opex_fraction * CAPEX_total + (energy_use_MWh * energy_price_USD/MWh). The lifecycle roll-up multiplies the total annual OPEX by the project life, and the total cost of ownership adds CAPEX and lifecycle OPEX. The verdict is a simple magnitude flag against a configurable CAPEX threshold.

This skill applies no CEPCI escalation, material or pressure factors, location factor, currency conversion, phasing, financing, depreciation, or abandonment cost. It is a transparent placeholder that must be replaced by a validated NeqSim cost estimate for any quantitative use.

Python Usage Pattern

from capex_opex_screening import CapexOpexModel

model = CapexOpexModel()
result = model.evaluate(
    bare_equipment_cost_musd=120.0,
    installation_factor=3.5,
    contingency_fraction=0.25,
    opex_fraction_of_capex_per_year=0.04,
    annual_energy_use_mwh=180000.0,
    energy_price_usd_per_mwh=60.0,
    project_life_years=20,
)

print(result.total_capex_musd)
print(result.total_annual_opex_musd)
print(result.total_cost_of_ownership_musd)
print(result.capex_warning)

Validated NeqSim Path

This screening is a placeholder. For real cost estimates use:

  • NeqSim CostEstimationCalculator — equipment-level CAPEX with Turton / Peters / Ulrich / Seider correlations, CEPCI escalation, material/pressure factors, and AACE class 1–5 (see the neqsim-equipment-cost-estimation skill).
  • The field-development DCF utilities in neqsim.process.util.fielddevelopment for CAPEX/OPEX phasing and cash-flow modelling (see neqsim-field-economics).
  • The NeqSim MCP runFieldEconomics tool for an orchestrated economics evaluation.

Escalation

Escalate any watch or high verdict, and any quantitative use, to a validated NeqSim cost estimate and qualified cost-engineering review.

Validation Checklist

  • Inputs are validated and within stated ranges.
  • Examples use public data only.
  • Screening assumptions are stated explicitly.
  • Limitations are respected.
  • Quantitative use is escalated to validated NeqSim models.

Common Mistakes

SymptomCauseFix
Unrealistic resultInputs outside the screening rangeKeep inputs within the stated bounds
Misused for designScreening output taken as finalEscalate to validated NeqSim models

Limitations

  • Educational screening only; not a validated design method.
  • No confidential data or proprietary methods are included.
  • Escalate any quantitative or design use to validated NeqSim workflows.

References

Download now (ZIP)

Does it work?

Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.

No reviews yet

People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.

  • It worked
  • Partly
  • It didn't
What did you use it for? e.g. Reviewing pull requests in a Rails app

Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.

Your trail

Files you open will collect here, so you can find them again.

Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.

Now do this for your own.

Bring your CLAUDE.md, AGENTS.md or skills. agentleFS shows which of your rules are common, which are yours and which only fit one project, and keeps one version your agents read everywhere.