Generates a project closure report aggregating data from charter, plan-fact report, risk register, and lessons learned. Last artifact of the Closing phase. Summarizes project outcomes, deviations, realized risks, and lessons. Triggers RU: «сформируй отчёт о закрытии», «закрой проект», «подготовь closure report», «отчёт о закрытии проекта». Triggers EN: 'generate closure report', 'close project', 'project closure report', 'prepare closure report'.

The file

Show its rules and text

We split this skill into the rules it gives an agent

20 rules. About 0 are common, 16 are distinctive, and 4 are very specific to this project.

  • ≈0

    Common · estimate

    Many files like this have a rule of this kind.

  • ≈16

    Distinctive · estimate

    This author's own choices. Worth a look.

  • 4

    Very specific

    Tied to their project's names, files or tools. Probably skip.

  • Common
  • Distinctive
  • Very specific
  1. Very specific:

    If the request is in Russian → use templates with -ru suffix

    line 16
  2. Distinctive:

    All output (headings, labels, comments, instructions) must match the detected language.

    line 19
  3. Distinctive:

    If required data is missing — request it (system-prompt-draft.md §3.2):

    line 34
  4. Distinctive:

    Verify input data: Check for minimum: charter, plan-fact report, lessons from user.

    line 52
  5. Distinctive:

    Structure lessons: If data is free-form — categorize into: Processes, Technologies, Communications, Resources, Risks.

    line 53
  6. Distinctive:

    Check data for contradictions: If charter data conflicts with plan-fact report (e.g., different planned dates or budget) — do NOT choose …

    line 54
  7. Very specific:

    If risk-register.md is available → extract risks with status "realized" or mentioned in user data.

    line 60
  8. Very specific:

    If risk-register.md is unavailable → use data from user.

    line 61
  9. Distinctive:

    If no risks occurred → replace the table with: "No realized risks".

    line 62
  10. Distinctive:

    Do not show system file paths.

    line 72
  11. Distinctive:

    Start and end dates (planned) — from charter (section 3).

    line 88
  12. Distinctive:

    If a deliverable is partially complete — list under "Delivered" with a "partial" note and description of what was excluded.

    line 97
  13. Distinctive:

    If budget was absent in plan-fact report — replace the budget row with "Budget — data unavailable".

    line 103
  14. Distinctive:

    If risks were realized — table with columns: ID, Risk, Project Impact, Response Result.

    line 110
  15. Distinctive:

    Do not include risks that were in the register but did not materialize.

    line 115
  16. Distinctive:

    If user provided lessons without categories — agent assigns based on content.

    line 124
  17. Distinctive:

    If open items exist — table: #, Item/Task, Owner, Deadline.

    line 130
  18. Distinctive:

    If no open items → replace the table with: "All items closed".

    line 133
  19. Distinctive:

    Before presenting the result to the user — verify:

    line 196
  20. Very specific:

    After report approval, user should upload closure-report.md to project knowledge for archival.

    line 226

≈ “Common” is an estimate: at least 1 in 5 of the 350,495 skill files we read have a rule of the same kind, not the same words. “Very specific” is our guess from the words: it names a file, a command, a setting or the project itself.

Keep what fits and drop the rest. Your version, ready for your agents.
Files
SKILL.md

generate-closure-report

Triggers

Russian: «сформируй отчёт о закрытии», «закрой проект», «подготовь closure report», «отчёт о закрытии проекта» English: "generate closure report", "close project", "project closure report", "prepare closure report"

Language Detection

Determine the language of the user's request:

  • If the request is in Russian → use templates with -ru suffix
  • Otherwise → use templates with -en suffix

All output (headings, labels, comments, instructions) must match the detected language.


1. Input Data

DataRequiredSourceNotes
Project charteryesknowledge (project-charter.md)Goal, deliverables, team, sponsor, budget, timeline
Plan-fact reportyesknowledge (plan-fact-report.md)Deviation summary, actual dates/budget/scope. If multiple files — use the latest by date
Lessons learnedyeschatUser provides in any format: retrospective results, questionnaire answers, free text. Agent structures and assigns categories
Risk registernoknowledge (risk-register.md)For section 4. If unavailable — agent asks the user about realized risks
Open itemsnochatTasks/questions remaining after closure. If not provided — replace section with "All items closed"
Lessons sourcenochatteam retrospective / questionnaire / PM input in chat. Default: PM input in chat

If required data is missing — request it (system-prompt-draft.md §3.2):

To generate the project closure report, the following is needed:
1. Project charter (project-charter.md) — in knowledge or paste in chat.
2. Plan-fact report (plan-fact-report.md) — in knowledge or paste in chat.
3. Project lessons — in any format:
   — team retrospective results;
   — questionnaire answers;
   — free-form description: what went well, what went wrong, what to do differently.
Available data: [list what is present].
Missing: [specify].

2. Execution Algorithm

  1. Verify input data. Check for minimum: charter, plan-fact report, lessons from user. Missing → request using the template from §1. Do NOT generate a stub report, template, or example — respond ONLY with a data request. Present → step 2.
  2. Structure lessons. If data is free-form — categorize into: Processes, Technologies, Communications, Resources, Risks. For each lesson — formulate a recommendation. Count: 1 to 5, only those supported by data. Do not pad artificially.
  3. Check data for contradictions. If charter data conflicts with plan-fact report (e.g., different planned dates or budget) — do NOT choose independently. List the discrepancies, ask which data is current. Exception: if the user explicitly corrects in chat — use the correction.
  4. Read the template closure-report from project knowledge. Select the file with the appropriate language suffix based on Language Detection.
  5. Fill section 1 (general information): planned data from charter, actual data from plan-fact report (summary).
  6. Fill section 2 (project results): list of deliverables from charter (section 2, "Project Result"). Actual status from plan-fact report (scope data) or from user. Split into "Delivered" / "Not delivered / deferred". For each incomplete deliverable — state the reason. If reason not provided — use [clarify].
  7. Fill section 3 (plan-fact deviations): copy the summary table from plan-fact-report.md (section 1). Data: plan, actual, deviation — without recalculation. Rephrase the "Comment" column in a closing tone (1 sentence per metric). At the bottom — reference: "Details — in plan-fact-report.md."
  8. Fill section 4 (realized risks):
    • If risk-register.md is available → extract risks with status "realized" or mentioned in user data. Verify: each risk in section 4 must have an ID from the register.
    • If risk-register.md is unavailable → use data from user. If user did not specify realized risks — ask: "Which planned risks were realized? If none — I will note 'No realized risks'."
    • If no risks occurred → replace the table with: "No realized risks".
  9. Fill section 5 (lessons learned): 1 to 5 lessons, structured in step 2. Category from the reference in §3.
  10. Fill section 6 (open items) and section 7 (closure approval):
    • Section 6: if user provided open items → fill in. If not → replace the table with: "All items closed".
    • Section 7: names from charter (Sponsor, PM). Dates — empty.
  11. Verify the result against the checklist (section 5 of this spec). Present the result in chat. Format (system-prompt-draft.md §3.4):
    • What was done: "Generated project closure report based on [list sources]".
    • Assumptions: list all (if any).
    • Key outcomes: 1–3 lines — main results (delivered X of Y, budget, timeline).
    • Required: "Approve, provide comments, or reject".
    • Do not show system file paths. Use name only: "Report saved as closure-report.md".
  12. Wait for user response (system-prompt-draft.md §3.5).
    • Approval → produce the final text.
    • Comments → revise, show updated version. After the 3rd iteration — ask: "Continue revising or finalize the current version?"
    • After approval:
      • Offer the user text to insert into log.md and project-state.md (system-prompt-draft.md §11).
      • State: "Closure report approved. Project completed." This is the final skill in the MVP chain — no subsequent tasks.

3. Section Fill Rules

Section 1. General Information

  • Project goal — from charter (section 1). Copy as-is, do not rephrase.
  • Sponsor — from charter (section 5 or header).
  • Start and end dates (planned) — from charter (section 3).
  • End date (actual) — from plan-fact report (last actual date) or from user. If project closes early — state the actual date with a note.
  • Budget (planned) — from charter (section 4). Budget (actual) — from plan-fact report (summary).

Section 2. Project Results

  • Delivered: each deliverable from charter (section 2, "Included") that is complete. Format: deliverable — brief result description.
  • Not delivered / deferred: deliverables that are incomplete or deferred. Format: deliverable — reason: [explanation]. If reason not provided by user — [clarify].
  • Status source: plan-fact report (scope data) > user data in chat.
  • If a deliverable is partially complete — list under "Delivered" with a "partial" note and description of what was excluded.

Section 3. Plan-Fact Deviations

  • Direct transfer of the summary table from plan-fact-report.md (section 1, 3 rows: timeline, budget, scope). Do not recalculate data.
  • "Comment" column — rephrase from plan-fact report in a closing tone. One sentence per metric. Example: "Delay +1 week due to Safari hotfix" → "Project completed with a +1 week delay; root cause — Safari incident during launch phase".
  • If budget was absent in plan-fact report — replace the budget row with "Budget — data unavailable".
  • Below the table — in italics: Details — in plan-fact-report.md.

Section 4. Realized Risks

Conditional section.

  • If risks were realized — table with columns: ID, Risk, Project Impact, Response Result.
  • ID — from risk-register.md (if available). If register unavailable — leave empty or assign R1, R2, ...
  • Project Impact — specific: what happened, what consequences (delay, overrun, scope change).
  • Response Result — what was done: did the response plan work, what actions were taken.
  • If no risks occurred → replace the table with: "No realized risks".
  • Do not include risks that were in the register but did not materialize.

Section 5. Lessons Learned

  • 1 to 5 lessons. Count is determined by user data — do not pad artificially.
  • Columns: #, Lesson, Category, Recommendation.
  • Category — from reference: Processes / Technologies / Communications / Resources / Risks.
  • Lesson — a fact or observation. Wording: what happened and why it matters.
  • Recommendation — a concrete action for future projects. Not an abstraction.
  • If user provided lessons without categories — agent assigns based on content.

Section 6. Open Items and Handover

Conditional section.

  • If open items exist — table: #, Item/Task, Owner, Deadline.
  • Owner — from user data. If not specified — [clarify].
  • Deadline — specific date (YYYY-MM-DD). If not specified — [clarify].
  • If no open items → replace the table with: "All items closed".

Section 7. Closure Approval

  • Sponsor and PM — from charter (section 5). Date — empty (filled upon approval).

Header Metadata

  • Version: 1.0
  • Date: current generation date.
  • File: closure-report.md
  • Document status: draft (on generation). After approval — approved.
  • Project manager: from charter.
  • Lessons source: from input data. Default: PM input in chat.

4. Placeholder Table

Placeholders {{}} in the template are fill guides, not auto-substitution variables. Replace each with the corresponding value from input data.

PlaceholderRequiredSourceAllowed Values
{{project_name}}yeschartertext
{{date}}yessystemYYYY-MM-DD
{{pm_name}}yeschartername
{{lessons_source}}yeschat (default: PM input in chat)team retrospective / questionnaire / PM input in chat
{{project_goal}}yescharter (section 1)text
{{sponsor_name}}yeschartername
{{planned_start}}yescharter (section 3)YYYY-MM-DD
{{planned_end}}yescharter (section 3)YYYY-MM-DD
{{actual_end}}yesplan-fact report / chatYYYY-MM-DD
{{planned_budget}}nocharter (section 4)number + currency
{{actual_budget}}noplan-fact reportnumber + currency
{{deliverable_N}}yes (≥1)charter (section 2)deliverable name
{{status_N}}yesplan-fact report / chatbrief result description
{{excluded_N}}nocharter / plan-fact reportundelivered deliverable name
{{reason_N}}nochat / plan-fact reportreason or [clarify]
{{planned_duration}}yesplan-fact report (summary)number + unit
{{actual_duration}}yesplan-fact report (summary)number + unit
{{delta_time}}yesplan-fact report (summary)text (e.g., "+1 week (+8%)")
{{comment_time}}yesagent (based on plan-fact report)closing comment, 1 sentence
{{delta_budget}}noplan-fact report (summary)text (e.g., "-$3,600 (-4.5%)")
{{comment_budget}}noagent (based on plan-fact report)closing comment, 1 sentence
{{planned_scope}}yesplan-fact report (summary)number + unit (deliverables)
{{actual_scope}}yesplan-fact report (summary)number + unit
{{delta_scope}}yesplan-fact report (summary)text (e.g., "-1 deliverable")
{{comment_scope}}yesagent (based on plan-fact report)closing comment, 1 sentence
{{risk_id}}norisk-register / agentID (e.g., R001) or empty
{{risk_description}}norisk-register / chatrisk description
{{impact}}nochat / agentspecific project impact
{{response_result}}nochat / agentresponse result
{{lesson_N}}yes (≥1)chat (structured by agent)text — fact/observation
{{category_N}}yesagentProcesses / Technologies / Communications / Resources / Risks
{{recommendation_N}}yesagentconcrete action
{{open_item_N}}nochatquestion or task
{{owner_N}}nochatowner or [clarify]
{{deadline_N}}nochatYYYY-MM-DD or [clarify]

5. Validation Checklist

Before presenting the result to the user — verify:

  • All required placeholders replaced with values
  • No {{}} placeholders remain in text (except removed optional rows)
  • Section 1: planned data matches charter, actual data matches plan-fact report
  • Section 2: all deliverables from charter listed (delivered + undelivered)
  • Section 2: each undelivered deliverable has a reason (or [clarify])
  • Section 3: data matches plan-fact report summary (no recalculation)
  • Section 3: reference to plan-fact-report.md present
  • Section 4: if conditional — correctly filled or replaced with "No realized risks"
  • Section 5: 1 to 5 lessons, each with category and recommendation
  • Section 6: if conditional — correctly filled or replaced with "All items closed"
  • All agent assumptions listed when presenting result
  • Document status = draft
  • File: closure-report.md stated in header

6. Dependencies

Consumes (input):

  • project-charter.md — from skill generate-charter (goal, deliverables, team, budget, timeline)
  • plan-fact-report.md — from skill generate-plan-fact-report (deviation summary, actual data)
  • risk-register.md — from skill generate-risk-register (optional, for realized risks)
  • Lessons and open items — from user (via chat)

Produces (output): project closure report — the final artifact. Not consumed by other MVP skills.

In Product 1: additionally consumes data from generate-questionnaire (team lessons via questionnaire).

After report approval, user should upload closure-report.md to project knowledge for archival.


7. Example Invocation

User command:

Generate the project closure report. Charter and plan-fact report are in knowledge. Risk register too. Lessons: — Underestimated DB filter complexity, lost a week. Need to budget buffer for unknown tasks. — Formalized change request saved us from scope creep — CEO wanted to add Intercom, but impact assessment stopped it. — Safari testing was done only before release — needs to happen earlier. Open items: — Email integration assigned to Dmitry, deadline July 31. — Pricing — on me, by August 1.

Agent response (after generation):

Generated project closure report for "ClientBoard" based on: charter, plan-fact report, risk register, lessons from chat.

Assumptions:

  • Lessons source: PM input in chat.
  • Realized risks identified based on risk-register.md and PM data.

Key outcomes:

  • Delivered 4 of 5 deliverables (email integration deferred).
  • Budget: $76,400 of $80,000 (4.5% savings).
  • Timeline: +1 week (13 instead of 12).

Required: approve, provide comments, or reject.

[report text]


Changelog

DateVersionChange
2026-03-261.0Skill created. Aggregation from charter + plan-fact report + lessons. Conditional sections 4/6. 1 to 5 lessons

Download now (ZIP)

Does it work?

Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.

No reviews yet

People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.

  • It worked
  • Partly
  • It didn't
What did you use it for? e.g. Reviewing pull requests in a Rails app

Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.

Your trail

Files you open will collect here, so you can find them again.

Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.

Now do this for your own.

Bring your CLAUDE.md, AGENTS.md or skills. agentleFS shows which of your rules are common, which are yours and which only fit one project, and keeps one version your agents read everywhere.