Checks scope against time and capacity: feature inventory, MoSCoW with effort caps, impact and risk scores, buffer math, scope-creep signals and a cut list, with velocity calibrated for AI-agent work and vibe debt counted as risk. Use for "scope creep", "can we fit this", "what should we cut", "are we on track". Not for sprint task planning (use game-sprint-plan).

The file

We split this skill into the rules it gives an agent

12 rules. About 0 are common, 10 are distinctive, and 2 are very specific to this project.

  • ≈0

    Common · estimate

    Many files like this have a rule of this kind.

  • ≈10

    Distinctive · estimate

    This author's own choices. Worth a look.

  • 2

    Very specific

    Tied to their project's names, files or tools. Probably skip.

  • Common
  • Distinctive
  • Very specific
  1. Distinctive:

    Ask up to three AskUserQuestion items, with defaults:

    line 57
  2. Distinctive:

    Effort caps: Must Haves take no more than 60% of estimated effort, with about 20% in Could Haves as contingency (the DSDM/Agile Business …

    line 65
  3. Distinctive:

    Freeze dates are real: No new features in the final days before a milestone (default three working days.

    line 71
  4. Very specific:

    Read ${CLAUDE_SKILL_DIR}/references/ai-velocity-calibration.md before estimating a project built with agents: it explains the evidence …

    line 117
  5. Distinctive:

    If you have never built something like a feature before, double its estimate.

    line 122
  6. Distinctive:

    Add external lead times as fixed blocks, not buffer: store and portal review (Engadget reported on 2026-11-04 that Steam build reviews were …

    line 185
  7. Distinctive:

    Write an ordered cut list now, in tiers with triggers, so cuts happen on schedule rather than in a panic: Tier 1 executes when buffer drops …

    line 227
  8. Very specific:

    Write the Scope Assessment Report to production/scope/YYYY-MM-DD-scope-check.md, hand the agreed scope to game-sprint-plan, send decisions …

    line 246
  9. Distinctive:

    Every feature has an hour estimate split by work type, or is explicitly UNKNOWN with a prototype task.

    line 334
  10. Distinctive:

    Must Haves at or under 60% of effort.

    line 337
  11. Distinctive:

    No feature scoring under 2.0 remains in Must or Should.

    line 339
  12. Distinctive:

    Every decision traces to scores, capacity math or a pillar, not to who argued hardest.

    line 342

≈ “Common” is an estimate: at least 1 in 5 of the 350,495 skill files we read have a rule of the same kind, not the same words. “Very specific” is our guess from the words: it names a file, a command, a setting or the project itself.

Keep what fits and drop the rest. Your version, ready for your agents.
Files
SKILL.md

AlterLab GameForge -- Scope Check

Games rarely die from one bad decision. They die from a feature list that grows one reasonable addition at a time until it no longer fits the team that has to finish it. Adding feels like progress and cutting feels like failure; this workflow inverts that. Cutting is the skill, and a tight scope is the achievement. A finished game with eight polished features beats an abandoned one with twenty half-built ones.

AI coding agents change the arithmetic but not the principle. They make the first playable and the boilerplate dramatically cheaper, which makes it easy to add features. They do not make integration, content, QA, polish or review proportionally cheaper, and unreviewed agent code creates debt that comes due later. The 2026 Vibe Jam gold winner, built with Claude Code in about two weeks (roughly 27k lines, 188+ commits, per Wccftech's July 2026 report on its workflow), was scoped to 5-10 minutes of play, and its creator built the 3D map by hand. Scope to what the whole pipeline can finish, not to how fast the prototype appeared.

Purpose & Triggers

Use this workflow when:

  • The feature list has grown since the last check, or nobody has ever done one.
  • Someone says "can we fit this in?" or "it'd only take the agent an hour."
  • A milestone, demo, festival or launch date is approaching and confidence is low.
  • Sprint velocity keeps missing plan, or agent sessions keep re-fixing the same systems.
  • The team feels overwhelmed and cannot say why.

Do NOT use this workflow when:

NeedRoute to
Turning the agreed scope into sprint tasksgame-sprint-plan
Making the final ship-date or scope call, risk register, milestonesgame-producer (this check feeds its decision)
De-risking one unknown feature before estimating itgame-prototype
Scoping a 48-72 hour jamgame-jam-mode
Assessing code health and refactor needs in detailgame-code-review, game-technical-director
Reviewing the design itselfgame-design-review
Looking back at why scope slippedgame-retrospective, game-postmortem

Inputs I Read First

  • .gameforge/project.json (phase, pillars), feature lists and the GDD in design/, sprint plans in production/sprints/, milestones in production/milestones/, previous checks in production/scope/, and production/session-state/active.md.
  • Git history as velocity evidence (read-only): git log --since="8 weeks ago" --oneline, git shortlog -sn --since="8 weeks ago", git diff --stat <last-milestone-tag>..HEAD, and the share of commits with agent co-author trailers. Real throughput beats remembered throughput.
  • Ask up to three AskUserQuestion items, with defaults:
    1. Deadline and what it is: demo or festival, early access, 1.0 launch, publisher milestone.
    2. Capacity: people x honest hours per week (default: one person, 15 h/week, part-time).
    3. How the code gets written: mostly by agents, mixed (default), mostly by hand.

Critical Rules

  1. One in, one out. Adding a feature means cutting one of equal effort. No "we'll work harder."
  2. Effort caps. Must Haves take no more than 60% of estimated effort, with about 20% in Could Haves as contingency (the DSDM/Agile Business Consortium MoSCoW guidance); Should Haves fill the rest. If Must Haves exceed 60%, the plan is at risk however important each feature feels.
  3. Score, don't debate. Disagreements challenge individual scores, not the outcome.
  4. Buffer is not optional. Below 20% buffer, expect to miss the date (rule of thumb). Buffer is for surprises, never for features.
  5. Freeze dates are real. No new features in the final days before a milestone (default three working days; a week before a festival or store submission).
  6. Estimate the whole feature. Design + code + content + integration + QA + polish + review. Agents speed up some of these and not others; estimate each part separately.
  7. Velocity comes from evidence. Plan from measured throughput on finished work, not from how fast a prototype appeared.
  8. Vibe debt is scope. Agent-written code nobody has reviewed, tested or understood is work that has not been done yet. Put its stabilization cost in the plan.
  9. Write the cut list before you need it. Decide what goes first while everyone is calm.

Workflow

PHASE 1: Feature Inventory

Catalog everything planned, in progress, requested or assumed. Do not filter yet.

FEATURE INVENTORY
ID   | Feature                 | Status       | Requested by | Pillar served
F01  | Grapple traversal       | in progress  | design       | "fluid movement"
F02  | Online co-op            | requested    | Discord      | --
F03  | Settings + rebinding    | assumed      | --           | (table stakes)

Probe for the hidden features that never make lists but always take time: settings, rebinding, save/load and save migration, controller support, pause and quit flows, basic accessibility options, localization hooks, tutorial or onboarding, credits, crash reporting, store page assets and trailer, demo build, platform builds (Steam Deck, web, mobile), achievements, AI-use disclosure and the asset provenance log, analytics consent. Read ${CLAUDE_SKILL_DIR}/references/cut-list-playbook.md for the full hidden-feature checklist and the cut techniques used in Phase 8.

PHASE 2: Estimate by Work Type, Calibrated for AI Agents

Estimate each feature in hours, split by work type, then apply the team's velocity ratios:

Work typeWith coding agents (planning assumption until measured)
Boilerplate, scaffolding, menus, data plumbing, debug toolsMuch faster
First prototype of one mechanicMuch faster
Integration with other systems, cross-system bugsLittle or no speedup; often slower if the code is unreviewed
Content: levels, writing, art direction, audioLittle speedup; AI assets add review, cleanup and provenance work
QA and playtestingNo speedup; more code shipped faster means more to test
Polish, juice, feelBound by human iteration and playtest cycles
Review of agent outputNew cost that hand-written code did not have

Read ${CLAUDE_SKILL_DIR}/references/ai-velocity-calibration.md before estimating a project built with agents: it explains the evidence behind each row, gives starting multipliers explicitly labeled as assumptions, and shows how to replace them with ratios measured from the project's own git history after two sprints.

If you have never built something like a feature before, double its estimate; if the engine or domain is new to the team, add 25-50% on top (rules of thumb). Mark anything you cannot estimate as UNKNOWN: an unknown is a prototype task, not a number.

PHASE 3: MoSCoW with Effort Caps

MUST HAVE (cap: 60% of effort) -- the game does not function or ship without it
  F01 Grapple traversal ........ 60 h  core verb, pillar "fluid movement"
  F03 Settings + rebinding ..... 18 h  table stakes; accessibility
  Subtotal: [X h] of [total] = [Y%]   -> OK / OVER

SHOULD HAVE -- notably better; a reviewer would notice it missing
  ...
COULD HAVE (about 20%: the contingency pool, first to go)
  ...
WON'T HAVE (this release) -- written down so it stops coming back
  F02 Online co-op ............. reason: networking risk, no pillar, 200+ h

Red flags: Won't Have is empty; Must Have over 60%; everything is Must Have (force-rank the Must Haves against each other and start again).

PHASE 4: Feature Scoring Matrix

Score = (Impact x Feasibility) / Risk, each 1-5.

Feature | Impact | Feasibility | Risk | Score | Verdict
F01     | 5      | 4           | 2    | 10.0  | KEEP
F02     | 3      | 1           | 5    | 0.6   | CUT
  • Impact: 5 core loop depends on it; 4 major experience gain; 3 reviewers would mention it; 2 minor polish; 1 players never see it.
  • Feasibility: 5 built this exact thing before; 3 understood but new; 1 nobody has done it. Score feasibility of shipping and maintaining it, not of the agent scaffolding it. "Claude wrote a netcode prototype in an evening" is feasibility 4 for the prototype and often 1-2 for shipped, server-authoritative multiplayer.
  • Risk: 5 could derail the project; 3 could slip a sprint; 1 low consequence.

Verdicts: 3.0 or higher KEEP; 2.0-3.0 EVALUATE (can risk drop or scope shrink?); below 2.0 CUT to Won't Have.

PHASE 5: Timeline and Buffer

CAPACITY
  People x honest hours/week x weeks remaining     = gross hours
  minus overhead (admin, community, marketing, ~15-25%) = net hours

WORK REMAINING (calibrated, Phase 2)
  Must + Should + Could                           = planned hours
  plus vibe-debt stabilization budget (Phase 6)   = total planned

BUFFER = net - total planned        BUFFER % = buffer / net
  30%+    GREEN   room for surprises
  20-30%  YELLOW  tight; no new features
  10-20%  ORANGE  one surprise from missing; execute the cut list's first tier
  <10%    RED     the date will be missed; cut now or move the date
  <0%     OVER    impossible as planned

Add external lead times as fixed blocks, not buffer: store and portal review (Engadget reported on 2026-11-04 that Steam build reviews were taking up to 12 business days against a 3-5 day target), console certification and resubmission, festival demo deadlines, localization turnaround.

PHASE 6: Vibe-Debt Assessment

Count agent-built debt as scope risk. Score each signal 0 (absent), 1 (some) or 2 (severe):

SignalHow to see it
Unreviewed agent code in core systemsCommits with agent co-author trailers touching core files that no human reviewed
Rework loopMany fix: commits on the same files; agent sessions re-fixing earlier fixes
Monolith growthOne file or scene holding most of the game (single-file web games past a few thousand lines are a common warning sign)
Thin testsFeature count rising faster than test count; no smoke test (see game-qa-lead)
Hard-coded tuningBalance numbers scattered through code (see game-balance-check)
Nobody can explain itThe team cannot describe how a core system works without asking the agent
Client-trusted stateMultiplayer or leaderboards that trust the client

0-3: normal; 4-7: add a stabilization budget (rule of thumb: 10-20% of remaining code hours); 8+: stop adding features until a stabilization sprint lands. Structural refactors are a Technical Director decision; route the evidence to game-technical-director and game-code-review.

PHASE 7: Scope-Creep Detection

Signal                                                        | Y/N
Feature list grew since last check                            |
Won't Have is empty                                           |
Everything is Must Have                                       |
Features added without an equal cut                           |
Estimates on existing features trending up                    |
Features arriving from casual chat or "the agent can do it"   |
Prototypes promoted to production without a rewrite decision  |
Buffer shrinking sprint over sprint                           |
Milestone date moved more than once                           |
Team morale falling despite visible "progress"                |
0-2 healthy | 3-4 early warning | 5-7 active creep | 8-10 full scope reset

PHASE 8: Cut List

Write an ordered cut list now, in tiers with triggers, so cuts happen on schedule rather than in a panic: Tier 1 executes when buffer drops below 20%, Tier 2 below 10%, Tier 3 if the date is fixed and buffer goes negative. For each candidate, prefer the cheapest technique that keeps the pillar: cut, shrink, fake, reuse, or defer to post-launch. Never cut save integrity, crash fixes, basic settings and accessibility, or compliance and disclosure work. The playbook reference has the techniques and template.

PHASE 9: Change Freeze

Milestone: [name] on [date]          Freeze: [date minus 3 working days; a week for festivals/submission]
After freeze, allowed:   bug fixes, polish on existing features, store assets, build pipeline
After freeze, banned:    new features of any size, scope changes, new assets for unbuilt features,
                         "quick" agent-generated additions
Breaking the freeze:     Producer approval + equal cut + written rationale; counts as a creep signal

PHASE 10: Report and Hand Off

Write the Scope Assessment Report to production/scope/YYYY-MM-DD-scope-check.md, hand the agreed scope to game-sprint-plan, send decisions needing authority to game-producer, and update production/session-state/active.md with the traffic-light status, the cuts made and the next check date.

Working with AI Coding Agents

What to delegate to the agent during a scope check

  • Building the feature inventory from the GDD, TODOs, issues and code (grep for TODO/FIXME, stubbed functions, feature flags).
  • Splitting estimates by work type and filling the scoring matrix as a first draft.
  • Summarizing git history: commits per week, fix-vs-feature ratio, files touched most often.

What the human decides

  • Impact scores and pillar fit. The agent does not know what makes the game worth playing.
  • Whether a prototype gets promoted, rewritten or thrown away.
  • What gets cut. The agent will happily keep everything.

Planning guardrails for agent-built games

  • The ten-minute feature is not ten minutes. A feature that took ten minutes to prompt still needs integration, content, tests, polish, review and support. Estimate those parts.
  • Prototype speed is not production velocity. Re-measure after two sprints of finished, reviewed, tested work; replace the starting multipliers with the measured ones.
  • Budget review time explicitly, as its own line, for every agent-built system that ships.
  • Keep the game original. Claude Code declines to recreate specific existing games (since late October 2026); scope features as your own design and genre mechanics, not as "X from game Y."
  • Distribution is scope too. With stores and portals flooded with fast-made games, budget real hours for store page, trailer, demo and community, not just features.

Pair with /gameforge:game-vibe-code for the build loop and /gameforge:game-ai-assets when AI assets are part of the content estimate.

Prompt that works: "Read design/ and production/sprints/, list every feature (including assumed ones like settings and save), and split each into design, code, content, integration, QA, polish and review hours. Use the multipliers in production/sprints/velocity.md. Mark anything you cannot estimate UNKNOWN. Do not classify or cut anything."

Output Format

# Scope Assessment Report -- [Project] -- [YYYY-MM-DD]
**Status:** [GREEN / YELLOW / ORANGE / RED / OVER] | **Milestone:** [name] on [date] | **Freeze:** [date]

## Summary
[2-3 sentences: overall assessment, key concern, recommended action.]

## Capacity and Buffer
| Net capacity | Planned work | Vibe-debt budget | External lead times | Buffer | Buffer % |
|---|---|---|---|---|---|
| 420 h | 290 h | 30 h | Steam review 12 business days | 100 h | 24% (YELLOW) |

## Velocity Basis
- Measured over [N] weeks: [x] features done, estimate accuracy [actual/estimate = 1.4],
  agent-assisted commits [y%], fix:feature commit ratio [z]
- Multipliers used: [measured / starting assumptions from the calibration reference]

## MoSCoW Breakdown
| Category | Features | Hours | % | Cap | Status |
|---|---|---|---|---|---|
| Must | 6 | 170 | 59% | <= 60% | OK |
| Should | 4 | 70 | 24% | -- | -- |
| Could | 3 | 50 | 17% | ~20% | OK |
| Won't | 5 | -- | -- | >= 2 items | OK |

## Feature Scores (descending)
| ID | Feature | I | F | R | Score | Verdict |
|---|---|---|---|---|---|---|

## Vibe-Debt Score: [n]/14 -- [normal / stabilization budget / stop and stabilize]
[Top signals with evidence]

## Scope-Creep Signals: [n]/10
[Active signals]

## Cut List
| Tier | Trigger | Feature | Technique | Hours saved | Pillar impact |
|---|---|---|---|---|---|
| 1 | Buffer < 20% | Weather system | Cut to post-launch | 26 h | none |
| 2 | Buffer < 10% | Boss 3 | Reuse boss 2 arena + new pattern | 30 h | low |

## Decisions Needed (owner)
1. [Decision] -- `game-producer`

## Next Check
[Date or trigger, e.g. end of sprint 6 or any new feature request]

Quality Criteria

  • Every feature has an hour estimate split by work type, or is explicitly UNKNOWN with a prototype task.
  • Velocity is grounded in measured history when history exists; starting multipliers are labeled.
  • Must Haves at or under 60% of effort; Won't Have has at least two items.
  • Buffer is calculated with external lead times and the vibe-debt budget included.
  • No feature scoring under 2.0 remains in Must or Should.
  • A tiered cut list with triggers exists, and nothing on the never-cut list is on it.
  • A freeze date is set for the next milestone.
  • Every decision traces to scores, capacity math or a pillar, not to who argued hardest.

Anti-Patterns

  • The Rubber Stamp: nothing gets cut because nobody wants the conflict. A check that cuts nothing was probably not honest.
  • The Hostage Feature: "we already started it." Sunk cost is not a reason; remaining cost versus value is.
  • The Stealth Add: features slip in without going through the matrix, often as "the agent already did a version of it."
  • The Ten-Minute Feature: prompt time mistaken for feature cost.
  • The Infinite Must Have: "I want this" confused with "the game needs this."
  • The Missing Buffer: "we'll just work harder." Buffer is reality insurance.

Cross-References

  • ${CLAUDE_PLUGIN_ROOT}/docs/game-design-theory.md: pillar alignment for Impact scores
  • ${CLAUDE_PLUGIN_ROOT}/docs/coordination-rules.md: escalation when scope conflicts arise
  • ${CLAUDE_PLUGIN_ROOT}/templates/sprint-plan.md: consumes this check's agreed scope
  • ${CLAUDE_PLUGIN_ROOT}/templates/game-pillars.md: the pillars features must serve
  • Receives input from game-brainstorm, game-design-review and game-gdd-author; feeds game-sprint-plan and game-producer.

Example Use Cases

  1. "Here's my feature list for a Steam Next Fest demo in 6 weeks. Can I fit it?"
  2. "Claude built most of the game in a month. Now everything takes forever. Are we over scope?"
  3. "We want to add online co-op. What do we cut to make room, and is it even feasible?"
  4. "Write us a tiered cut list for the 1.0 launch before we need it."
  5. "Measure our real velocity from git and tell me whether the March date is realistic."

Download now (ZIP)

Does it work?

Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.

No reviews yet

People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.

  • It worked
  • Partly
  • It didn't
What did you use it for? e.g. Reviewing pull requests in a Rails app

Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.

Your trail

Files you open will collect here, so you can find them again.

Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.

Now do this for your own.

Bring your CLAUDE.md, AGENTS.md or skills. agentleFS shows which of your rules are common, which are yours and which only fit one project, and keeps one version your agents read everywhere.