Project management for BI projects. Use when the user mentions: project plan, sprint, milestone, delivery, roadmap, stakeholder, requirements, scope, backlog, user story, epic, data product, product management, agile, kanban, release plan, go-live, risk, RAID log, data platform delivery, data project, BI delivery, analytics delivery, change management, business case.

The file

Files
SKILL.md

Skill: Project & Product Management — Data Platform Delivery

Trigger

Activate when the user mentions: project plan, sprint, milestone, delivery, roadmap, stakeholder, requirements, scope, backlog, user story, epic, data product, product management, agile, kanban, release plan, go-live, risk, RAID log, data platform delivery, data project, BI delivery, analytics delivery, change management, business case

What You Know

You have delivered enterprise data platforms from inception to production — managing stakeholders, scope, teams of 5–30 people, budgets, and the inevitable last-minute requirement changes. You know what kills data projects and how to prevent it.

The Data Product Mindset

Think of every analytical output as a data product, not a report. A data product has:

  • An owner (accountable person, not just a team)
  • Consumers (who uses it and how)
  • A SLA (refresh frequency, availability, acceptable error rate)
  • A lifecycle (v1, v2, deprecation)
  • Feedback loops (usage metrics, consumer satisfaction)

Project Phases — Data Platform Delivery

Phase 1: Discovery & Design (2–4 weeks)
  ├── Stakeholder interviews (business requirements)
  ├── Source system analysis (data availability, quality)
  ├── Data model design (star schema, grain decisions)
  ├── Architecture decision (Fabric, medallion, DirectLake)
  └── Delivery plan + RAID log

Phase 2: Foundation (2–4 weeks)
  ├── Fabric workspace setup + access control
  ├── Medallion architecture scaffolding
  ├── CI/CD pipeline setup (GitHub/ADO)
  └── Source connections + Bronze ingestion

Phase 3: Core Delivery (4–8 weeks, sprints of 2 weeks)
  ├── Silver transformations (cleansing, SCD, type alignment)
  ├── Gold layer (star schema, aggregations)
  ├── Semantic model (DAX measures, RLS, descriptions)
  └── MVP report (executive summary + 1–2 operational views)

Phase 4: Hardening & UAT (2–3 weeks)
  ├── Data quality tests + reconciliation
  ├── Performance tuning (V-Order, aggregations, Incremental Refresh)
  ├── RLS testing (all user profiles)
  └── UAT with business stakeholders

Phase 5: Go-Live & Hypercare (2–4 weeks)
  ├── Production deployment
  ├── User training and onboarding
  ├── Hypercare period (daily check-ins, fast bug fixes)
  └── Handover documentation

Agile Delivery for Data Projects

Epic → Story → Task structure

Epic: Sales Analytics Data Product
  Story: Bronze ingestion from CRM
    Task: Set up Fabric lakehouse connection to Salesforce
    Task: Create Bronze ingestion notebook
    Task: Validate Bronze row counts match source
  Story: Silver customer dimension
    Task: Design dim_customer schema (SCD Type 2)
    Task: Build Silver transformation notebook
    Task: Write pytest test suite for dim_customer
  Story: Total Sales measure
    Task: Implement [Total Sales] DAX measure
    Task: Write DAX test for known CY2023 value
    Task: Add measure description and format string

Story Points — Data Project Calibration

1 pt  → Simple column rename, measure description update
2 pt  → New measure with 1 dependency, simple table column
3 pt  → New measure with time intelligence, SCD implementation
5 pt  → New data source integration, complex DAX pattern
8 pt  → Full Silver table with quality tests, new Fabric connection
13 pt → End-to-end data product (source → Gold → semantic model)

RAID Log (Risks, Assumptions, Issues, Dependencies)

## RAID Log — Sales Analytics Platform

### Risks
| ID | Risk | Probability | Impact | Mitigation | Owner |
|---|---|---|---|---|---|
| R1 | CRM API rate limiting delays Bronze loads | Medium | High | Implement retry + incremental windows | Data Eng |
| R2 | Historical data quality issues > 2019 | High | Medium | Scope to 2020+ initially; backfill in Phase 2 | PM |

### Assumptions
| ID | Assumption | If Wrong... | Owner |
|---|---|---|---|
| A1 | Source CRM data has consistent email format | Data normalisation effort increases by 2 sprints | Data Eng |
| A2 | Business users will test during UAT sprint | Go-live delayed by minimum 1 sprint | PM |

### Issues
| ID | Issue | Severity | Resolution | Owner | Due |
|---|---|---|---|---|---|
| I1 | ERP database has no modified_date column | High | Full load only; re-assess CDC options | Data Eng | Sprint 2 |

### Dependencies
| ID | Dependency | Provider | Due | Risk if Missed |
|---|---|---|---|---|
| D1 | Fabric workspace provisioned | IT Admin | Sprint 1 | All development blocked |
| D2 | CRM API credentials | CRM team | Sprint 1 | Bronze ingestion blocked |

Stakeholder Communication Templates

Weekly Status Update

## Analytics Platform — Week 12 Status

**Overall Status:** 🟢 ON TRACK

**This Week:**
- ✅ Silver customer dimension completed + tested
- ✅ DAX measures: [Total Sales], [Sales YTD], [YoY%] done
- ⚠️ ERP connection delayed — IT provisioning issue (see Risk R2)

**Next Week:**
- Bronze ingestion: Orders fact table
- Silver transformation: fact_orders
- Begin UAT preparation checklist

**Open Issues:**
- I1: ERP modified_date column missing → full load approach agreed

**Ask of Stakeholders:**
- Business team: Please confirm UAT start date (currently planned Week 15)

Go-Live Checklist

☐ All pipelines running on schedule with no failures for 5+ days
☐ UAT signed off by business sponsor
☐ RLS tested for all user profiles (incl. edge cases)
☐ Performance: all report pages load < 3 seconds
☐ Incremental refresh configured on fact tables
☐ Alerts configured for pipeline failures (email + Teams)
☐ Support runbook documented (common issues + resolution steps)
☐ Training session delivered to end users
☐ Rollback plan documented
☐ Go-live communication sent to all stakeholders

Data Product Metrics (Post Go-Live)

Track these to demonstrate value:

# Report usage stats from Power BI Service
pbi-agent fabric usage-report --workspace "Analytics Platform" --days 30

# Check pipeline success rate
pbi-agent fabric pipeline-health --workspace "Analytics Platform" --days 14
  • Adoption: Daily active users / target users
  • Reliability: Pipeline success rate (target: >99%)
  • Performance: Average page load time (target: <3s)
  • Quality: Data reconciliation pass rate (target: 100%)
  • Satisfaction: Monthly user NPS survey

Download now (ZIP)

Does it work?

Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.

No reviews yet

People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.

  • It worked
  • Partly
  • It didn't
What did you use it for? e.g. Reviewing pull requests in a Rails app

Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.

Your trail

Files you open will collect here, so you can find them again.

Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.

Now do this for your own.

Bring your CLAUDE.md, AGENTS.md or skills. agentleFS shows which of your rules are common, which are yours and which only fit one project, and keeps one version your agents read everywhere.