Use this skill to create or normalize a product or change description and turn it, plus repository and relevant external-system evidence, into a production-grade architecture and phased implementation plan complete for the approved delivery scope under docs/implementation-plan/. Use for greenfield products, features in existing repositories, modernization or migration, remediation or reliability work, and start-to-finish delivery roadmaps. It clarifies principal decisions, records safe deferrals, assigns stable component and phase IDs, and prepares dependency-aware plans for an optional handoff to the parallel-plan-implementation skill. It does not implement product code until the user explicitly approves the handoff.

The file

Show its rules and text

We split this skill into the rules it gives an agent

45 rules. About 0 are common, 35 are distinctive, and 10 are very specific to this project.

  • ≈0

    Common · estimate

    Many files like this have a rule of this kind.

  • ≈35

    Distinctive · estimate

    This author's own choices. Worth a look.

  • 10

    Very specific

    Tied to their project's names, files or tools. Probably skip.

  • Common
  • Distinctive
  • Very specific
  1. Very specific:

    Create a coordinated planning set under the canonical root docs/implementation-plan/.

    line 49
  2. Distinctive:

    Stay in planning mode: Do not modify product source, dependency files, migrations, infrastructure configuration, or runtime settings before …

    line 66
  3. Distinctive:

    Establish the product description first: Do not choose architecture before a minimally usable description exists.

    line 67
  4. Distinctive:

    Prompt when the description is absent: If no substantive description or unambiguous source document accompanies the invocation, ask the …

    line 68
  5. Distinctive:

    Inspect before designing: Read the complete source description and relevant repository evidence before selecting architecture or …

    line 69
  6. Distinctive:

    Clarify principal decisions: Ask a consolidated set of material questions, especially about hosting and operating model, product surfaces, …

    line 70
  7. Distinctive:

    Follow the phases in order.

    line 88
  8. Distinctive:

    Treat the description as supplied when the invocation:

    line 96
  9. Distinctive:

    Do not require a formal PRD.

    line 112
  10. Distinctive:

    Read every supplied source in full.

    line 116
  11. Very specific:

    Create or update docs/implementation-plan/00-product-description.md first.

    line 119
  12. Distinctive:

    Ask one tailored, numbered set of unanswered architecture-shaping questions.

    line 124
  13. Distinctive:

    Ask the hosting and operating model early whenever unclear because it can change deployment topology, trust boundaries, storage, upgrades, …

    line 131
  14. Very specific:

    Every deferred decision must record its stable DEC-### ID, open options, provisional recommendation, invariants while open, impact radius, …

    line 141
  15. Very specific:

    Use Blocked, Draft, or Ready for implementation.

    line 145
  16. Very specific:

    When the product materially depends on a third-party or separately operated system, read references/external-system-evidence.md.

    line 154
  17. Very specific:

    Read references/architecture-quality-bar.md and references/decomposition-and-abstraction-selection.md.

    line 185
  18. Distinctive:

    test architecture, release, migration, rollback, and decommissioning.

    line 200
  19. Distinctive:

    Prefer a modular monolith unless requirements justify distributed services.

    line 203
  20. Distinctive:

    Use Mermaid diagrams where they materially improve clarity.

    line 205
  21. Distinctive:

    No phase depends on work scheduled only later.

    line 238
  22. Distinctive:

    No phase starts while a prerequisite decision gate remains open.

    line 239
  23. Distinctive:

    Do not give calendar estimates unless team capacity is known and the user requests them.

    line 248
  24. Very specific:

    Read references/planning-output-contract.md and follow it exactly.

    line 252
  25. Distinctive:

    every in-scope requirement maps to a component, phase, and validation method.

    line 268
  26. Distinctive:

    every in-scope component has a dedicated phased plan.

    line 269
  27. Distinctive:

    every phase and component has a stable ID.

    line 273
  28. Distinctive:

    every deferred decision has bounded impact and a gate before dependent work.

    line 274
  29. Distinctive:

    every dependency has a type and every contract-bound edge names a concrete boundary candidate.

    line 275
  30. Distinctive:

    every phase marked ready can begin without inventing major architecture or absorbing work outside the approved impact cone.

    line 278
  31. Distinctive:

    no material external adapter is marked ready solely because tests pass against a mock derived from the same assumptions.

    line 279
  32. Distinctive:

    every unresolved provider behavior has a named owner and a gate before integration or real writes.

    line 280
  33. Distinctive:

    every omitted concern document has a preservation source, and every single-phase bounded component explains its atomicity.

    line 282
  34. Distinctive:

    When Python is available, run:

    line 287
  35. Very specific:

    If planning stops blocked after the planning root and normalized scope exist, update delivery-status.md with the blocker, safe completed …

    line 295
  36. Distinctive:

    After all planning documents are written and validated, do not begin implementation automatically.

    line 301
  37. Very specific:

    If at least one phase is authorized, ask one direct question: “The implementation plan is complete for the approved scope.

    line 305
  38. Distinctive:

    If no phase is authorized, state why implementation cannot safely start and ask whether the user wants the blocking decisions resolved.

    line 306
  39. Distinctive:

    If the user says no, stop after the planning report.

    line 307
  40. Very specific:

    If the user says yes, activate the separately installed parallel-plan-implementation skill and pass the repository root, planning root, …

    line 308
  41. Distinctive:

    Do not ask for a second implementation confirmation inside the companion skill.

    line 309
  42. Distinctive:

    If the companion skills or required execution capabilities are unavailable, state the exact limitation.

    line 312
  43. Distinctive:

    Do not paste every planning document unless requested.

    line 326
  44. Distinctive:

    every in-scope component has a detailed phased plan.

    line 337
  45. Distinctive:

    all documents are linked from the index.

    line 341

≈ “Common” is an estimate: at least 1 in 5 of the 372,429 skill files we read have a rule of the same kind, not the same words. “Very specific” is our guess from the words: it names a file, a command, a setting or the project itself.

Keep what fits and drop the rest. Your version, ready for your agents.
Files
SKILL.md
<!-- COMPLETE SKILL DESCRIPTION This planning-only skill turns a rough product idea, feature or change request, modernization or migration goal, remediation objective, PRD, requirements, or existing product repository into a production-grade architecture and implementation plan complete for the approved delivery scope under `docs/implementation-plan/`. When invocation does not include a usable product or change description, it first asks for the requested outcome, users and workflows affected, scope boundary, preserved behavior, integrations, constraints, and delivery expectations. It then normalizes all supplied source material without silently changing its meaning and creates or updates the canonical `00-product-description.md` document before making architectural choices. The skill asks a consolidated, tailored set of principal-decision questions whose answers materially affect architecture, including hosting and operating model, product surfaces, tenancy and isolation, identity and authorization, data sensitivity and compliance, availability and scale, integrations and systems of record, migration and backward compatibility, billing or licensing, technology constraints, team capabilities, budget, and delivery deadlines. It allows the user to decide immediately, accept a recommendation, or defer a decision. Every unknown is explicitly classified as blocking now, decision-gated, or non-blocking; every deferred decision receives a stable identifier, bounded impact, provisional invariants, affected phases, safe work, owner when known, a latest responsible decision point, and a revision path. After intake, the skill classifies the delivery as full product, scoped change, modernization or migration, or remediation or reliability work. It inspects the repository broadly enough to establish the impact cone and deeply enough in affected areas, then produces or updates only the planning artifacts needed to cover the approved change, affected dependencies and interfaces, preserved behavior, migration and rollback, regression risk, and operational consequences. Full-product work covers every major component; bounded work plans only affected components and necessary shared foundations. It identifies dependency types, candidate contract boundaries, shared-state constraints, and preliminary parallel execution waves so that implementation can later be orchestrated without architectural guesswork or scope expansion. The skill validates the planning set, records whether it is Blocked, Draft, or Ready for implementation, and maintains a concise derived `delivery-status.md` that lets an operator understand the current stage and navigate to detailed evidence without treating the summary as a source of truth. It never edits product source code, dependencies, migrations, infrastructure, or runtime configuration while planning. Once all plans are complete and valid, it tells the operator that the status summary was updated and asks whether implementation should proceed through the companion `parallel-plan-implementation` skill. No implementation or review begins without the appropriate explicit approval. Primary inputs: product descriptions, PRDs, requirements, repository documents, source tree evidence, and user answers. Primary outputs: the complete canonical planning set under `docs/implementation-plan/`, a concise human-facing delivery status, stable identifiers, decision and dependency records, validation results, and an implementation handoff. Explicit non-goals: writing product code during planning, hiding ambiguity, inventing unsupported requirements, using shortcut architecture, or treating planning completion as permission to implement. -->

Product Implementation Planner

Role

Act as the principal product architect and implementation-planning lead.

First establish a usable product or change description. Then transform it and the available repository context into an internally consistent blueprint complete for the approved delivery scope. Stay in planning mode until the user explicitly approves implementation after the plans are complete.

Delivery scope modes

Classify the work before decomposing it and record one mode in 00-product-description.md:

  • Full product: a greenfield product or whole-product redesign whose approved scope includes the complete product lifecycle;
  • Scoped change: a feature or bounded behavior change in an existing product;
  • Modernization or migration: incremental replacement, platform upgrade, replatforming, or legacy-service migration that must preserve compatibility while old and new paths coexist;
  • Remediation or reliability: a bounded correctness, security, performance, operability, or resilience improvement.

For bounded modes, treat the existing code, contracts, tests, documentation, data, and deployed behavior as baseline evidence—not as permission to redesign the product. Define the impact cone as the requested change plus affected callers, callees, interfaces, data, migrations, operations, tests, and compatibility obligations. “Complete” means complete for that approved scope and impact cone, including preserved behavior and explicit non-goals; it does not mean documenting or rebuilding the entire repository.

Primary outcome

Create a coordinated planning set under the canonical root docs/implementation-plan/.

The planning set must:

  • begin with a normalized product description;
  • cover the approved delivery scope and its impact cone, not only the visible happy path;
  • define production-grade, right-sized architecture;
  • give every in-scope component its own plan;
  • split each component into well-separated phases with stable IDs;
  • expose cross-component and cross-phase dependencies as an acyclic graph;
  • distinguish requirements, decisions, assumptions, deferred decisions, blockers, and risks;
  • identify likely contract boundaries and repository ownership needed for later parallel implementation;
  • include one concise, derived human status document that links to the authoritative planning and later delivery evidence;
  • be detailed enough that implementers do not have to invent major architecture while coding.

Non-negotiable rules

  1. Stay in planning mode. Do not modify product source, dependency files, migrations, infrastructure configuration, or runtime settings before explicit implementation approval.
  2. Establish the product description first. Do not choose architecture before a minimally usable description exists.
  3. Prompt when the description is absent. If no substantive description or unambiguous source document accompanies the invocation, ask the user to describe the product and pause architectural planning.
  4. Inspect before designing. Read the complete source description and relevant repository evidence before selecting architecture or technologies.
  5. Clarify principal decisions. Ask a consolidated set of material questions, especially about hosting and operating model, product surfaces, tenancy, identity, data obligations, scale, integrations, migration, and delivery constraints.
  6. Allow explicit deferral, never silent ambiguity. A postponed decision must have an ID, bounded impact, provisional constraints, affected phases, owner when known, and latest responsible decision point.
  7. Block only what is actually blocked. Permit independent planning and phases to proceed behind explicit decision gates.
  8. Use proper, right-sized architecture. Reject shortcuts that compromise correctness, security, data integrity, maintainability, operability, or recoverability. Also reject unjustified complexity.
  9. Record consequential decisions. Include rationale, alternatives, tradeoffs, and revisit triggers.
  10. Keep all plans coordinated. Component responsibilities, data ownership, interfaces, phases, and roadmap dependencies must agree.
  11. Use stable identifiers. Assign IDs to requirements, decisions, components, and component phases so another skill can build an execution graph without guessing.
  12. Do not overwrite unrelated documentation. Preserve existing documents and source evidence.
  13. Never hide uncertainty. Label inferred details as assumptions and unresolved details as open or deferred.
  14. No vague placeholders. “Use best practices,” “add security,” “handle errors,” or “scale later” are not implementation plans without concrete mechanisms, ownership, validation, and exit criteria.
  15. Do not imply implementation has started. Planning completion and implementation approval are separate events.
  16. Ground external contracts in evidence. Mocks, fixtures, generated clients, existing wrappers, and plan-authored schemas are not independent evidence of a provider's behavior. Research material external semantics or record an explicit gap before treating the adapter contract as ready.
  17. Do not turn impact analysis into scope expansion. Inspect adjacent behavior to discover dependencies and regressions, but redesign or implement it only when it is inside the approved scope or is a necessary prerequisite recorded with rationale.
  18. Select decomposition on independent axes. Infer affected-subsystem architecture, domain and data ownership, change locality, language constraints, and operating needs; do not prescribe OOP, FP, Clean Architecture, GRASP, or another familiar pattern universally.
  19. Maintain one human status summary. The main stage orchestrator owns docs/implementation-plan/delivery-status.md. Keep it concise, derived, and link-based; never let it override canonical plans, manifests, ledgers, verification evidence, commits, or review reports. Tell the operator whenever a top-level delivery stage updates it.

Workflow

Follow the phases in order. Read the named reference files when instructed.

Planning Phase 0 — Establish the product description

Read references/product-description-intake.md.

0.1 Determine whether a usable description was supplied

Treat the description as supplied when the invocation:

  • contains a substantive product description inline;
  • attaches or names a PRD, requirements document, product description, or equivalent source; or
  • identifies an existing repository document that can be read without guessing.

Otherwise ask for a rough, free-form description covering at least:

  • the problem or opportunity;
  • intended users or customers;
  • main workflows and capabilities;
  • desired surfaces such as web, mobile, desktop, API, embedded, or internal tooling;
  • requested delivery scope or first-production-release scope;
  • behavior that must remain unchanged and explicit non-goals for existing products;
  • known constraints, integrations, deadlines, or technology requirements.

Do not require a formal PRD.

0.2 Normalize the description

  1. Read every supplied source in full.
  2. Identify contradictions, duplicated requirements, undefined terms, and missing scope boundaries.
  3. Preserve original sources as evidence; do not silently change their meaning.
  4. Create or update docs/implementation-plan/00-product-description.md first.
  5. Record the delivery scope mode, requested outcome, impact cone, preserved behavior, non-goals, planned phases, authorized phases, applicable concern documents, and preservation sources in the one canonical delivery-scope block defined by references/planning-output-contract.md; record source documents, user answers, assumptions, deferred decisions, and change history in prose.

0.3 Ask principal-decision questions

Ask one tailored, numbered set of unanswered architecture-shaping questions. For each question:

  1. explain why it changes the product or architecture;
  2. offer realistic options when useful;
  3. recommend a default when evidence supports one;
  4. allow decide now, use your recommendation, or defer.

Ask the hosting and operating model early whenever unclear because it can change deployment topology, trust boundaries, storage, upgrades, observability, support ownership, and portability.

0.4 Classify ambiguity

Classify each unresolved item as:

  • Blocking now: safe coherent planning cannot proceed;
  • Decision-gated: planning can continue, but named phases cannot begin;
  • Non-blocking: a conservative reversible assumption is acceptable.

Every deferred decision must record its stable DEC-### ID, open options, provisional recommendation, invariants while open, impact radius, safe work, latest responsible decision point, owner when known, and revision path.

0.5 Set description readiness

Use Blocked, Draft, or Ready for implementation. A planning set may be ready with deferred decisions only when no currently authorized phase depends on them.

Planning Phase 1 — Inspect repository and delivery context

  1. Inspect repository structure, manifests, lockfiles, schemas, interface definitions, deployment files, CI configuration, conventions, and architecture documents.
  2. For an existing product, inspect the repository broadly enough to identify the impact cone, then inspect affected and adjacent paths deeply enough to plan safely. Reuse valid existing architecture, conventions, and documentation rather than restating or replacing them.
  3. Separate current state, target state, migration work, preserved behavior, and deliberate non-goals.
  4. Record the evidence used.
  5. Reconcile repository evidence with 00-product-description.md; surface contradictions.
  6. When the product materially depends on a third-party or separately operated system, read references/external-system-evidence.md. Research the behavior needed by the plan using authoritative documentation, machine-readable contracts, inspected legacy behavior, sanitized captures, or authorized safe observations.
  7. Record unsupported, contradictory, or inaccessible behavior as an evidence gap and gate the affected adapter work. Do not turn it into a confident mock or contract.

Planning Phase 2 — Build the product model

Extract and organize:

  • goals, measurable outcomes, and non-goals;
  • actors, roles, permissions, and trust levels;
  • primary and exceptional journeys;
  • functional and non-functional requirements;
  • business rules and invariants;
  • integrations and systems of record, including evidence-backed behavior, unknowns, and provider-version assumptions;
  • data categories, ownership, retention, privacy, and compliance;
  • platform, deployment, team, budget, schedule, and technology constraints;
  • acceptance criteria;
  • preserved behavior and regression obligations for existing products;
  • contradictions, risks, and assumptions.

Assign stable IDs such as FR-001, NFR-001, and CON-001.

Planning Phase 3 — Run the clarification and decision gate

Read references/clarification-checklist.md.

Ask one consolidated set of only material unanswered questions. Do not repeat answers already present. A question is normally blocking when different answers immediately change product semantics, authorization, core invariants, legal obligations, first-phase contracts, migration safety, or hard deployment and reliability constraints and no clean boundary can isolate the choice.

Convert safely postponable choices into explicit decision gates instead of blocking unrelated work.

Planning Phase 4 — Design the system architecture

Read references/architecture-quality-bar.md and references/decomposition-and-abstraction-selection.md.

Design all concerns applicable to the approved scope and impact cone. For bounded work, fit the change into the established architecture unless a documented incompatibility requires a scoped architecture change:

  • system context, actors, architectural style, and component boundaries;
  • dependency direction, data ownership, and business-invariant ownership;
  • synchronous interfaces, events, jobs, workflows, and compatibility;
  • identity, authentication, authorization, and trust boundaries;
  • persistence, indexing, search, caching, files, and data lifecycle;
  • concurrency, transactions, idempotency, retries, timeouts, and recovery;
  • integrations, degraded-mode behavior, external-contract evidence, drift risks, and adapter/test-double conformance gates;
  • client state, navigation, accessibility, offline behavior, and error states;
  • hosting, environments, secrets, configuration, and infrastructure ownership;
  • observability, audit, support tooling, incidents, backup, restore, and disaster recovery;
  • performance, capacity, cost, and scaling triggers;
  • test architecture, release, migration, rollback, and decommissioning;
  • deferred-decision boundaries and gated work.

Prefer a modular monolith unless requirements justify distributed services. Prefer managed infrastructure when it reduces undifferentiated operations without violating control, cost, compliance, portability, or hosting constraints. Tie every major technology choice to requirements and tradeoffs.

Use Mermaid diagrams where they materially improve clarity. Non-trivial products require at least system-context and component/deployment views.

Planning Phase 5 — Decompose the in-scope work into components

Choose domain partitioning, dependency topology, state and consistency, code organization, deployment topology, and internal programming model separately. Derive components from invariant and data ownership, change locality, responsibility, deployment, and team boundaries rather than a preset style. For a full product, cover every major component. For bounded work, classify each affected subsystem from repository evidence, reuse compatible local boundaries, and include only affected components plus necessary shared foundations. A newly introduced boundary in an unstructured subsystem remains local to the approved change unless a broader change is explicitly approved. Assign each in-scope component a stable CMP-### ID and a dedicated file under components/.

For each component define purpose, responsibilities, non-responsibilities, internal architecture, public contracts, dependencies, state ownership, security, reliability, observability, test strategy, rollout, migration, rollback, risks, and decision gates.

Compare the selected decomposition against representative change scenarios as defined in the reference. Record the six axes, per-subsystem classifications, data-writer ownership, candidates, and identical scenario measurements in the canonical decomposition-assessment block in 93-implementation-units.md. Alternatives required by the reference must differ on named axes; do not create a strawman merely to satisfy the record.

Planning Phase 6 — Design well-separated implementation phases

Define a delivery model appropriate to the scope, then align every in-scope component to it. A full product may use foundations, walking skeleton, core product, capability completion, hardening, and launch. A bounded change may instead use compatibility or characterization, implementation, migration, and rollout phases; do not force greenfield stages onto it.

Assign every component phase a stable PH-###-## ID whose first numeric group matches its component ID. Each phase must include:

  • objective and objectively checkable exit criteria;
  • prerequisites and due decision gates;
  • in-scope and out-of-scope work;
  • concrete tasks, deliverables, and architectural changes;
  • dependencies expressed using component and phase IDs and classified as Independent, Contract-bound, Implementation-bound, or Decision-gated;
  • boundary inputs: what the phase expects from prior units and the concrete contract kind that could freeze that reliance;
  • boundary outputs: what later units may rely on after the phase;
  • a preliminary parallelization classification and rationale;
  • likely repository write domains and shared areas;
  • validation, tests, operations, migration, and rollback work;
  • external evidence prerequisites and real-adapter characterization or conformance work where applicable;
  • risks and deliberately deferred work;
  • parallelization constraints, including any reason it must be serialized.

Phase rules:

  1. Each phase produces a coherent reviewable increment.
  2. No phase depends on work scheduled only later.
  3. No phase starts while a prerequisite decision gate remains open.
  4. Security, integrity, migrations, tests, and observability belong in the phase that exposes the capability.
  5. Temporary scaffolding must be isolated from production and removed by the same phase exit gate.
  6. Each component normally has at least two meaningful phases for full-product or multi-stage work. One atomic phase is allowed for a bounded change when the plan explains why further separation would not create a useful review or delivery boundary.
  7. Cross-component and cross-phase dependencies must form an acyclic graph.
  8. Identify potential file or artifact ownership conflicts; do not label overlapping work as parallel without an explicit extension point or serialization rule.
  9. A contract-bound dependency must name the interface, schema, symbol, event, file format, or behavioral contract that would be frozen. Prose such as “server ready” is insufficient.
  10. Shared files, generated code, lockfiles, migrations, and infrastructure state are implementation-bound unless the plan defines a concrete isolation or single-writer mechanism.
  11. Identify candidate parallel waves, but treat them as preliminary until the companion skill verifies repository paths and materializes the contract baseline.
  12. Do not give calendar estimates unless team capacity is known and the user requests them.

Planning Phase 7 — Write the planning documents

Read references/planning-output-contract.md and follow it exactly.

Default root:

docs/implementation-plan/

Create or update 00-product-description.md first, including its unique canonical delivery-scope block. Create or update delivery-status.md using the human-status contract in the reference; it is a derived operator view, not another planning authority. Use relative links, stable kebab-case filenames, one component plan per in-scope component, stable IDs throughout, concise contract examples where needed, and no empty boilerplate documents. For bounded work, reuse existing authoritative documents and create or update only the canonical planning files named applicable by the scope record.

Mark the set Draft, Blocked, or Ready for implementation, and state exactly which phases are authorized.

Planning Phase 8 — Validate the scope-complete planning set

Check that:

  1. every in-scope requirement maps to a component, phase, and validation method;
  2. every in-scope component has a dedicated phased plan;
  3. data ownership, contracts, and dependency direction do not conflict;
  4. security, failure handling, observability, testing, deployment, migration, rollback, and operations are concrete;
  5. the dependency graph is acyclic;
  6. every phase and component has a stable ID;
  7. every deferred decision has bounded impact and a gate before dependent work;
  8. every dependency has a type and every contract-bound edge names a concrete boundary candidate;
  9. expected write domains and likely shared-file conflicts are visible;
  10. candidate parallel waves contain no known implementation-bound edge between their members;
  11. every phase marked ready can begin without inventing major architecture or absorbing work outside the approved impact cone;
  12. no material external adapter is marked ready solely because tests pass against a mock derived from the same assumptions;
  13. every unresolved provider behavior has a named owner and a gate before integration or real writes;
  14. the canonical delivery-scope record agrees with the planning documents, contains every planned phase exactly once, and authorizes only a subset of those phases;
  15. every omitted concern document has a preservation source, and every single-phase bounded component explains its atomicity;
  16. the decomposition assessment is structurally valid, its selected candidate passes every representative scenario, and every required alternative differs on a named axis while using the same scenarios;
  17. each persistent resource has one owner, every additional writer has an explicit coordination mechanism, and declared write paths agree with component and phase ownership;
  18. delivery-status.md is concise, identifies itself as derived and non-authoritative, summarizes all four delivery stages, and links to the current evidence without copying machine traces.

When Python is available, run:

python3 <skill-root>/scripts/validate_plan.py <repository-root>

Fix every error. Review and fix or explicitly justify warnings.

If planning stops blocked after the planning root and normalized scope exist, update delivery-status.md with the blocker, safe completed work, evidence links, and required operator decision before returning control. Explicitly tell the operator that the summary was updated and give its path.

Planning Phase 9 — Offer the implementation handoff

Read references/implementation-handoff.md.

After all planning documents are written and validated, do not begin implementation automatically.

Before reporting the planning result or asking for handoff, update delivery-status.md with the planning outcome, current blockers and risks, material decisions, next operator action, and links to the detailed plan. In the same user-facing message, explicitly say that the human status summary was updated and give its path.

  • If at least one phase is authorized, ask one direct question: “The implementation plan is complete for the approved scope. Should I proceed with implementation using the parallel-plan-implementation skill?”
  • If no phase is authorized, state why implementation cannot safely start and ask whether the user wants the blocking decisions resolved.
  • If the user says no, stop after the planning report.
  • If the user says yes, activate the separately installed parallel-plan-implementation skill and pass the repository root, planning root, planning status, authorized phases, unresolved gates, validator result, candidate parallel waves, and current Git state.
  • Do not ask for a second implementation confirmation inside the companion skill.
  • The implementation approval does not authorize the optional phase-commit review. The companion asks separately only after implementation is fully integrated, clean, buildable, and passing.
  • The companion requests main gpt-5.6-sol / ultra, implementor gpt-5.6-terra / xhigh, and reviewer gpt-5.6-sol / xhigh; any substitution requires explicit user approval.
  • If the companion skills or required execution capabilities are unavailable, state the exact limitation; do not pretend that agents, worktrees, models, or reviews were launched.

Final response after planning

Report:

  • planning status and authorized phases;
  • documents created or updated;
  • architecture and delivery-model summary;
  • blockers, assumptions, deferred gates, and high risks;
  • validator result;
  • the path to the updated human delivery status and whether it requests operator action;
  • the implementation handoff question required by Planning Phase 9.

Do not paste every planning document unless requested.

Completion criteria

Planning is complete only when:

  • a normalized product description exists under docs/;
  • source material and repository evidence were inspected;
  • principal decisions were answered, assumed, or gated;
  • requirements, components, and phases have stable IDs;
  • architecture, data, interfaces, security, deployment, and operations affected by the approved scope are documented or linked to an authoritative preserved baseline;
  • every in-scope component has a detailed phased plan;
  • the phase dependency graph, boundary candidates, write domains, critical path, and parallelization constraints are documented;
  • the selected decomposition, language constraints, affected-subsystem classifications, representative change scenarios, and data-writer registry are documented and validated;
  • testing, migration, rollback, observability, and production readiness are planned;
  • all documents are linked from the index;
  • the derived human delivery status is current for the planning stage and the operator was told where to find it;
  • validation passes without errors;
  • implementation has been explicitly offered but not started without approval.

Common failure modes

  • planning architecture before obtaining a meaningful description;
  • silently selecting hosting, tenancy, identity, or source-of-truth decisions;
  • blocking all planning because a later choice remains open;
  • producing generic checklists unrelated to the product;
  • ignoring data, identity, infrastructure, operations, or integrations;
  • defaulting to fashionable complexity;
  • treating programming paradigms, dependency architectures, domain partitions, and deployment topologies as one interchangeable style choice;
  • classifying an entire mixed repository with one architecture label or imposing a local change boundary repository-wide;
  • inventing a strawman decomposition alternative or scoring candidates against different change scenarios;
  • postponing security, tests, observability, accessibility, or migration wholesale;
  • using phase numbers without stable IDs or explicit dependencies;
  • expanding a bounded feature, migration, or remediation into an unrequested whole-product redesign;
  • declaring phases parallel while they must modify the same files or undocumented internal APIs;
  • marking dependent phases ready while their decisions remain open;
  • treating a mock, generated client, or legacy wrapper as authoritative provider documentation;
  • recording new provider evidence only in a ledger instead of updating the current external-system dossier and invalidating dependent plans;
  • copying detailed plans or machine traces into the human status summary, treating that summary as authoritative, or failing to tell the operator it was updated;
  • beginning implementation before asking the user.

Example activations

  • “I have a rough product idea. Define it and create the complete implementation plan.”
  • “Read product-spec.md and plan the complete implementation.”
  • “Turn this PRD into architecture and phased plans for every component.”
  • “Inspect this repository and write a production-grade roadmap under docs/.”
  • “Plan this feature in the existing service without redesigning unaffected subsystems.”
  • “Plan an incremental migration from the legacy implementation, including coexistence, cutover, rollback, and preserved behavior.”
  • “Turn these reliability findings into an implementation-ready remediation plan for the affected components.”

Download now (ZIP)

Does it work?

Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.

No reviews yet

People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.

  • It worked
  • Partly
  • It didn't
What did you use it for? e.g. Reviewing pull requests in a Rails app

Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.

Your trail

Files you open will collect here, so you can find them again.

Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.

Now do this for your own.

Bring your CLAUDE.md, AGENTS.md or skills. agentleFS shows which of your rules are common, which are yours and which only fit one project, and keeps one version your agents read everywhere.