Write a production deployment plan covering environment specs, deployment strategy (Blue-Green, Canary, Rolling, or Direct), step-by-step execution runsheet, go/no-go criteria, monitoring plan, and rollback procedure. Use before any non-trivial production release.

2 other projects use a version of this.

Adopted by

Most recently taken up by

The file

Show its rules and text

We split this skill into the rules it gives an agent

31 rules. About 0 are common, 26 are distinctive, and 5 are very specific to this project.

  • ≈0

    Common · estimate

    Many files like this have a rule of this kind.

  • ≈26

    Distinctive · estimate

    This author's own choices. Worth a look.

  • 5

    Very specific

    Tied to their project's names, files or tools. Probably skip.

  • Common
  • Distinctive
  • Very specific
  1. Distinctive:

    Rolling Deploy: Update instances one at a time.

    line 40
  2. Distinctive:

    When risk is high and downtime is unacceptable but infrastructure is limited, invest in the infrastructure before deploying - do not paper …

    line 58
  3. Distinctive:

    When deploying changes that span multiple services, document the dependency graph and deployment order explicitly:

    line 62
  4. Distinctive:

    Rollback coordination: If service A is rolled back, must services B and C also roll back?

    line 65
  5. Distinctive:

    When the deployment includes IaC changes (Terraform, Pulumi, CloudFormation, CDK), treat infrastructure changes with the same rigor as …

    line 70
  6. Very specific:

    Plan before apply: Always run terraform plan (or equivalent) and review the diff before applying.

    line 71
  7. Distinctive:

    State management: Ensure remote state is locked during the deployment window.

    line 73
  8. Distinctive:

    Drift detection: Before deploying, check for configuration drift between the IaC state and actual infrastructure.

    line 75
  9. Distinctive:

    DNS TTL: If changing DNS records, lower TTL to 60-300 seconds at least 24 hours before the deployment.

    line 80
  10. Distinctive:

    Certificate provisioning: If deploying to a new domain or subdomain, ensure certificates are provisioned and validated before the …

    line 81
  11. Distinctive:

    Multi-domain / SAN certificates: If the service serves multiple domains, verify all SANs are covered.

    line 83
  12. Distinctive:

    Incident-triggered freezes: After a SEV-1 or SEV-2 incident, enforce a deployment freeze for [N hours] while the team stabilizes and …

    line 103
  13. Distinctive:

    Synthetic monitoring: Run automated user journey tests against production every [N minutes] post-deployment.

    line 110
  14. Distinctive:

    Automated rollback trigger: If verification automation detects a failure, it should trigger automatic rollback without waiting for human …

    line 113
  15. Distinctive:

    When deploying to containerized environments (Kubernetes, ECS), additional considerations apply:

    line 117
  16. Very specific:

    Image tagging: Never deploy with the latest tag.

    line 118
  17. Distinctive:

    Readiness and liveness probes: Ensure the new image's health endpoints are compatible with the configured probes.

    line 120
  18. Distinctive:

    Helm chart / Kustomize changes: If the deployment modifies Helm values or Kustomize overlays, treat these as infrastructure changes with …

    line 122
  19. Distinctive:

    Before deploying to production, verify a defined set of criteria.

    line 126
  20. Distinctive:

    When your analysis conflicts with the user's stated preference:

    line 136
  21. Distinctive:

    If the document is significantly shorter than the target, check for:

    line 154
  22. Very specific:

    Interview Mechanism: Use tool calls (e.g., AskUserQuestion) to present questions — do NOT ask inline in the conversation.

    line 163
  23. Very specific:

    Context Loading: Before asking ANY questions, read ALL prior documents in .engineering-docs/ to extract already-known information.

    line 165
  24. Distinctive:

    Maximum 2-3 questions per skill: Only ask about:

    line 174
  25. Distinctive:

    Ask questions to resolve:

    line 179
  26. Distinctive:

    Document the exact execution runsheet - every command, every verification step.

    line 187
  27. Distinctive:

    If the user requests changes after reviewing the document:

    line 194
  28. Distinctive:

    Deploying without a written rollback plan: If you cannot articulate the rollback steps before deploying, you are not ready to deploy.

    line 205
  29. Distinctive:

    Forgetting to disable feature flags during rollback: If the deployment enabled feature flags, the rollback must disable them.

    line 209
  30. Very specific:

    Before marking this document as final, verify:

    line 229
  31. Distinctive:

    After this document is complete, proceed to:

    line 244

≈ “Common” is an estimate: at least 1 in 5 of the 350,495 skill files we read have a rule of the same kind, not the same words. “Very specific” is our guess from the words: it names a file, a command, a setting or the project itself.

Keep what fits and drop the rest. Your version, ready for your agents.
Files
SKILL.md

Purpose

Produce a deployment plan that specifies exactly how, when, and by whom a release is deployed, what criteria determine success or failure, and what steps to take if something goes wrong.

A deployment without a rollback plan is a deployment without a safety net. This skill ensures every production change is made with eyes open and a clear path back.

Input

Works best with: The name of the service being deployed and a description of what is changing. Also valuable: Current production environment specs, existing deployment pipeline, known risks or dependencies, SLA requirements.

Example invocation: Write a deployment plan for releasing PayFlow v2.4.0 to production. This release includes 3 database migrations (additive only), a new webhook delivery queue worker, and updates to the checkout templates. We use a single production server with PHP-FPM and MySQL. Zero downtime is required.

Key Concepts

Deployment Strategies

  • Direct Deploy: Replace running code in-place. Simple, but brief downtime risk.
  • Rolling Deploy: Update instances one at a time. No downtime. If failure occurs, some instances run old code while others run new.
  • Blue-Green: Maintain two identical environments (Blue = current, Green = new). Switch traffic at load balancer after validation. Zero downtime. Full instant rollback by switching back.
  • Canary: Deploy to small percentage of traffic first (e.g., 5%). Monitor. Gradually increase if metrics hold.
  • Feature Flag: Deploy code to all servers but enable via config. Decouple deployment from release.

Strategy Decision Matrix

Choose the deployment strategy based on three factors: risk tolerance, downtime tolerance, and infrastructure capability.

Risk LevelDowntime OK?InfrastructureRecommended Strategy
LowYesSingle serverDirect Deploy
LowNoMultiple instancesRolling Deploy
MediumNoLoad balancer availableBlue-Green
HighNoLoad balancer + metrics pipelineCanary
AnyNoFeature flag system in placeFeature Flag
HighNoKubernetes / ECSCanary with pod-level rollback

When risk is high and downtime is unacceptable but infrastructure is limited, invest in the infrastructure before deploying - do not paper over the gap with manual vigilance.

Multi-Service/Microservice Deployment Coordination

When deploying changes that span multiple services, document the dependency graph and deployment order explicitly:

  • Deployment ordering: Which service deploys first? Which depends on which? Use a directed acyclic graph (DAG) to visualize.
  • Backward compatibility window: During a multi-service rollout, both old and new versions of each service must coexist. Document the compatibility contract for each interface change.
  • Rollback coordination: If service A is rolled back, must services B and C also roll back? Define this before the deployment begins.
  • Shared schema changes: Database migrations that affect multiple services require a coordinated deployment sequence - typically: migrate schema (backward-compatible) -> deploy consumers -> deploy producers -> remove old columns.

Infrastructure-as-Code (IaC) Changes

When the deployment includes IaC changes (Terraform, Pulumi, CloudFormation, CDK), treat infrastructure changes with the same rigor as application code:

  • Plan before apply: Always run terraform plan (or equivalent) and review the diff before applying. Document the expected changes in the deployment plan.
  • Blast radius assessment: Which resources will be created, modified, or destroyed? Destroying and recreating a database is not the same as updating a security group rule.
  • State management: Ensure remote state is locked during the deployment window. Concurrent applies cause state corruption.
  • Rollback for IaC: Infrastructure rollbacks are often harder than code rollbacks. If a terraform apply creates a new load balancer, rolling back requires another apply, not just a symlink swap. Document the IaC rollback steps explicitly.
  • Drift detection: Before deploying, check for configuration drift between the IaC state and actual infrastructure. Drift means the plan may not apply cleanly.

DNS and TLS Certificate Management

DNS and certificate changes have unique timing characteristics that must be planned:

  • DNS TTL: If changing DNS records, lower TTL to 60-300 seconds at least 24 hours before the deployment. After the change is stable, raise TTL back. Document the TTL reduction step in the pre-deployment checklist.
  • Certificate provisioning: If deploying to a new domain or subdomain, ensure certificates are provisioned and validated before the deployment window. Automated provisioning (Let's Encrypt) can fail due to DNS propagation delays or rate limits.
  • Certificate expiry monitoring: Confirm no certificates in the deployment chain expire within 30 days. An expired certificate during a deployment window is a self-inflicted outage.
  • Multi-domain / SAN certificates: If the service serves multiple domains, verify all SANs are covered.

Canary Deployment Metrics Comparison

For canary deployments, define the metrics comparison methodology before the deployment:

  • Comparison tool: How will canary metrics be compared to baseline? (Prometheus queries, Datadog monitors, custom dashboard)
  • Comparison thresholds: What metric deltas trigger automatic rollback vs. manual review vs. automatic promotion?
    • Error rate: canary must not exceed baseline by more than [X%]
    • Latency: canary p99 must not exceed baseline p99 by more than [Y ms]
    • Business metrics: canary success rate must not drop below [Z%]
  • Promotion criteria: What is the exact decision logic?
    1. Canary at 5% for 15 minutes, all metrics within thresholds -> promote to 25%
    2. Canary at 25% for 30 minutes, all metrics within thresholds -> promote to 100%
    3. Any threshold breach at any stage -> automatic rollback
  • Promotion authority: Who approves the final promotion from canary to full rollout? Automated, or requires human sign-off?

Deployment Freeze Windows

Define periods when deployments are prohibited or restricted:

  • Scheduled freeze windows: Holidays, end-of-quarter, major business events, audit periods. Document these in the deployment plan.
  • Incident-triggered freezes: After a SEV-1 or SEV-2 incident, enforce a deployment freeze for [N hours] while the team stabilizes and recovers.
  • Freeze exceptions: Who can authorize a deployment during a freeze? What is the approval process?
  • Freeze communication: How are freeze windows communicated to the team? (Shared calendar, Slack announcement, deployment tool enforcement)

Post-Deployment Verification Automation

Automate post-deployment verification to catch regressions faster than manual smoke tests:

  • Synthetic monitoring: Run automated user journey tests against production every [N minutes] post-deployment. Tools: Checkly, Datadog Synthetics, custom scripts.
  • Canary analysis automation: Automatically compare canary vs. baseline metrics and produce a pass/fail verdict.
  • Deployment health scorecard: A single dashboard that aggregates all post-deployment checks (health endpoint, error rate, latency, queue depth, business metrics) into a pass/fail status.
  • Automated rollback trigger: If verification automation detects a failure, it should trigger automatic rollback without waiting for human intervention (for deployments where this is safe).

Container/Orchestration Specifics

When deploying to containerized environments (Kubernetes, ECS), additional considerations apply:

  • Image tagging: Never deploy with the latest tag. Use immutable, version-specific tags (e.g., sha-abc1234 or v2.4.0).
  • Resource limits: Define CPU and memory requests/limits in the deployment manifest. Deploying without limits risks noisy-neighbor issues or OOM kills.
  • Readiness and liveness probes: Ensure the new image's health endpoints are compatible with the configured probes. A failed readiness probe means the pod never receives traffic; a failed liveness probe means the pod gets killed repeatedly.
  • Rolling update strategy: Configure maxSurge and maxUnavailable to control the rollout speed. Too aggressive risks capacity loss; too conservative wastes deployment window time.
  • Helm chart / Kustomize changes: If the deployment modifies Helm values or Kustomize overlays, treat these as infrastructure changes with the same plan-before-apply discipline.
  • ECS-specific: For ECS, document the task definition revision, service update configuration (minimum healthy percent, maximum percent), and whether the deployment uses rolling update or blue/green via CodeDeploy.

Go/No-Go Gate

Before deploying to production, verify a defined set of criteria. If any criterion fails, the deployment does not proceed. This is not optional.

DORA Metrics (What Good Looks Like)

  • Deployment Frequency: Elite teams deploy multiple times per day.
  • Lead Time for Change: Elite teams go from commit to production in less than 1 hour.
  • Change Failure Rate: Elite teams have < 5% deployments causing failures.
  • MTTR: Elite teams recover from failures in less than 1 hour.

Conflict Resolution

When your analysis conflicts with the user's stated preference:

  1. Present both positions — show your analysis and their preference side by side
  2. Explain the trade-off — what are the consequences of each choice?
  3. Recommend with reasoning — state your recommendation and why
  4. Respect the user's decision — they own the final call
  5. Document the decision — record it as an [owner-specified] override with reasoning

Document Length

Target length: 5-10 pages (excluding appendices).

Shorter is better than longer. If the document exceeds the target, check for:

  • Redundant content that can be cut
  • Overly verbose explanations
  • Content that belongs in a separate reference document
  • Material the agent already knows (don't explain what HTTP is)

If the document is significantly shorter than the target, check for:

  • Missing sections
  • Insufficient detail in critical areas
  • Unaddressed edge cases

Application

Phase 1: Socratic Clarification & Brainstorming (Mandatory Interview)

Interview Mechanism: Use tool calls (e.g., AskUserQuestion) to present questions — do NOT ask inline in the conversation. The user selects from options rather than typing responses. One question per tool call, multiple-choice options preferred, with "I don't know, you decide" as an escape hatch.

Context Loading: Before asking ANY questions, read ALL prior documents in .engineering-docs/ to extract already-known information. Look for:

  • Team size, budget, timeline (from business-plan)
  • Tech stack, hosting (from system-architecture)
  • Target users, JTBD (from user-personas)
  • Constraints, regulatory requirements (from business-plan)
  • Scope, features (from technical-specification)

If information exists in a prior document, USE IT — do not re-ask.

Maximum 2-3 questions per skill. Only ask about:

  • Skill-specific details not covered in prior documents
  • Technical decisions that affect this specific document
  • Clarifications on ambiguous requirements

Ask questions to resolve:

  1. Current deployment workflow: What tools (GitHub Actions, manual rsync, Ansible) execute the deploy?
  2. Downtime limits: Is any brief service interruption acceptable, or is a zero-downtime strategy (Blue-Green, Canary) mandatory?

Wait for the user's response to these questions before drafting the final deployment plan.

Phase 2: Document Generation

  1. Choose the deployment strategy based on the risk profile and infrastructure.
  2. Document the exact execution runsheet - every command, every verification step.
  3. Define explicit go/no-go criteria with measurable thresholds.
  4. Define the rollback procedure before you start.
  5. Identify the on-call owner who will monitor the deployment.

Phase 3: Revision (After User Review)

If the user requests changes after reviewing the document:

  1. Read the user's feedback carefully — understand what they want changed
  2. Check for conflicts — does the requested change conflict with prior documents (e.g., technical specification, system architecture)?
  3. Apply changes — update the deployment plan
  4. Re-run consistency check — verify the change doesn't break cross-document consistency (e.g., rollback steps still match the architecture's infrastructure)
  5. Update metadata — set last_updated to today's date
  6. Confirm with user — show the changes and get approval

Gotchas

  • Deploying without a written rollback plan. If you cannot articulate the rollback steps before deploying, you are not ready to deploy. The rollback plan must be written, reviewed, and tested on staging before the deployment window opens.
  • Running database migrations after application code deployment. If the migration is backward-compatible, run it before the new code deploys so old code still works with the new schema. If it is not backward-compatible, it needs a multi-phase migration strategy - not a single deploy.
  • Skipping the post-deployment monitoring window. Declaring "deploy complete" and walking away means no one catches the slow-burn failure (memory leak, queue backup, gradual error rate increase). Monitor for at least 30 minutes after smoke tests pass.
  • Defining go/no-go criteria as subjective gut feelings. "Looks good" is not a go/no-go criterion. Use measurable thresholds: error rate below X%, p99 latency below Y ms, specific smoke test passes. If you cannot measure it, you cannot decide on it.
  • Forgetting to disable feature flags during rollback. If the deployment enabled feature flags, the rollback must disable them. A code rollback without flag rollback leaves the system in an inconsistent state where old code is running but new behavior is partially enabled.

Handoff

Reads from:

  • 1-business-plan.md — business constraints, uptime requirements
  • 5-technical-specification.md — performance and reliability requirements
  • 7-system-architecture.md — infrastructure topology, tech stack
  • 15-test-strategy.md — test gates that must pass before deployment
  • 14-implementation-plan.md — feature scope, migration requirements

Feeds into:

  • 17-technical-runbook.md — post-deployment monitoring procedures
  • 18-disaster-recovery.md — infrastructure context for failover planning
  • 19-slo-error-budget.md — deployment impact on reliability targets

Quality Gate

Before marking this document as final, verify:

  • The rollback procedure is complete with numbered steps, estimated time, and was tested on staging
  • Every go/no-go criterion is measurable and binary (pass/fail, not "looks okay")
  • The execution runsheet includes exact commands, not just descriptions of what to do
  • Monitoring thresholds are defined with specific numeric values and corresponding actions
  • A deployment lead and on-call backup are both named and confirmed available for the deployment window
  • If deploying to containers/Kubernetes: image uses an immutable tag, resource limits are defined, and readiness/liveness probes are verified
  • If canary strategy: promotion criteria are defined with specific metric thresholds and comparison tool
  • If multi-service: deployment order DAG is documented, backward compatibility window is defined, and coordinated rollback plan exists
  • If IaC changes: terraform plan output reviewed, blast radius assessed, and IaC-specific rollback steps documented
  • If DNS/TLS changes: TTL pre-lowered, certificate provisioning verified, and expiry checked
  • Deployment freeze windows checked and documented (or exception authorized)

Next Steps

After this document is complete, proceed to:

  • technical-runbook — document operational procedures for monitoring and responding to alerts post-deployment
  • disaster-recovery-plan — define RTO/RPO targets and failover procedures for the deployed system
  • slo-error-budget-document — formalize reliability targets and error budget policies
  • Or invoke using-engineering-docs to continue the pipeline

Download now (ZIP)

Does it work?

Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.

No reviews yet

People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.

  • It worked
  • Partly
  • It didn't
What did you use it for? e.g. Reviewing pull requests in a Rails app

Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.

Your trail

Files you open will collect here, so you can find them again.

Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.

Now do this for your own.

Bring your CLAUDE.md, AGENTS.md or skills. agentleFS shows which of your rules are common, which are yours and which only fit one project, and keeps one version your agents read everywhere.