Inventories tech debt and ranks it economically - scoring each item 1-3 on cost of delay (the interest rate) and leverage (the principal unblocked), multiplying into a priority index, and packaging the winners into a leadership proposal framed on business impact. Use when someone asks "which tech debt should we tackle first", "help me build a case for refactoring to leadership", "our backlog of debt is huge, where do we start", or is preparing quarterly planning. Do NOT use for finding and removing unused code - use dead-code-eliminator instead - for auditing third-party dependency risk - use dependency-risk-audit - or for planning the sprint the work lands in - use sprint-planning instead.

The file

We split this skill into the rules it gives an agent

8 rules. About 0 are common, 7 are distinctive, and 1 is very specific to this project.

  • ≈0

    Common · estimate

    Many files like this have a rule of this kind.

  • ≈7

    Distinctive · estimate

    This author's own choices. Worth a look.

  • 1

    Very specific

    Tied to their project's names, files or tools. Probably skip.

  • Common
  • Distinctive
  • Very specific
  1. Distinctive:

    Do not filter the inventory before scoring - pre-filtering re-introduces the vibes the scoring exists to remove.

    line 71
  2. Very specific:

    Do not use a finer scale than 1-3.

    line 72
  3. Distinctive:

    Do not pitch leadership on code quality, elegance, or "best practices" - pitch interest payments and unblocked roadmap.

    line 73
  4. Distinctive:

    Do not schedule low-CoD/high-leverage items standalone.

    line 74
  5. Distinctive:

    Do not let the parking lot skip its quarterly review.

    line 75
  6. Distinctive:

    Do not put an XL item on the quarter plan un-decomposed.

    line 76
  7. Distinctive:

    Every inventory item traces to one of the three signal sources.

    line 80
  8. Distinctive:

    Every item has both axis scores, an index, and a quadrant - no unscored pet projects smuggled into "do now".

    line 81

≈ “Common” is an estimate: at least 1 in 5 of the 350,495 skill files we read have a rule of the same kind, not the same words. “Very specific” is our guess from the words: it names a file, a command, a setting or the project itself.

Keep what fits and drop the rest. Your version, ready for your agents.
Files
SKILL.md

Tech Debt Prioritizer

Tech debt decisions fail when made on vibes ("this code is ugly") or recency bias (whatever hurt last week). This skill applies a lightweight economic frame - debt as a loan, where cost of delay is the interest rate you pay every sprint and leverage is the principal of future work it unblocks - so the right items get funded and the rest stay parked without guilt.

Operating procedure

The steps run in order because scoring an unfiltered inventory is what keeps the ranking honest: filtering first means the loudest complaints survive and the quiet, expensive items never get scored.

Step 1: gather inputs and build the inventory

Timebox to 60 minutes and cap the list at 20 items - past 20, scoring fatigue produces garbage scores. Pull candidates from three sources, one pass each:

  • Friction signals: team retros and chat complaints.
  • Reliability signals: incident post-mortems from the last two quarters.
  • Velocity signals: areas with high cycle time or frequent reverts.

Each item gets a one-line description, the system it lives in, and the person who raised it. Do not filter at this stage; resist the urge. If an estimate is a gut call ("this costs us maybe a day a sprint"), record it as a guess.

Step 2: score each item on two axes, 1-3 each

  • Cost of delay (the interest rate): what does leaving this unaddressed cost per sprint - engineer time lost, incident risk carried, opportunity cost? 1 = an annoyance under a few hours a sprint; 2 = meaningful drag, roughly half a day to two days of engineer time per sprint or a plausible incident path; 3 = actively bleeding - multiple engineer-days per sprint, a repeat-incident source, or blocking a committed date.
  • Leverage (the principal): how many future features or workflows does fixing this unblock or accelerate? 1 = local cleanup, nothing downstream; 2 = speeds up one team's ongoing work; 3 = unblocks multiple roadmap items or teams.

Multiply for the priority index (1-9). Items scoring 9 are immediate candidates; 6 goes on the quarter plan; 1-2 goes to the parking lot. Score in one sitting with the whole group so the scale stays calibrated across items.

Step 3: classify by quadrant

Plot on a 2x2 to catch what the index alone hides:

  • High cost-of-delay / high leverage: do now.
  • High cost-of-delay / low leverage: schedule this quarter - the interest is real even if nothing downstream is waiting.
  • Low cost-of-delay / high leverage: opportunistic - fold into adjacent feature work rather than scheduling standalone.
  • Low / low: document and defer to the parking lot.

The parking lot needs a quarterly review gate that drops items older than 6 months. An unbounded parking lot becomes a second backlog nobody trusts.

Step 4: size and assign

Every "do now" and "this quarter" item gets a t-shirt size (S = days, M = 1-2 weeks, L = 3-6 weeks, XL = needs decomposition before it can be scheduled - an XL debt item is a project, not a task). Propose an owner per item, and do not assign all debt to the same two senior engineers: well-scoped debt work is a career-growth opportunity for mid-level engineers, and hoarding it on seniors makes it invisible and unpromotable.

Step 5: write the proposal

Lead with business impact, never code quality. The sentence pattern per item: "This currently costs us X per sprint / caused incident Y / blocks initiative Z. Fixing it takes N engineer-weeks. The expected return is [time recovered, risk retired, or roadmap unblocked]." Skip the architecture lecture - leadership funds interest-rate reduction, not elegance. If stakeholders resist all debt investment, propose a debt tax: reserve 15-20% of each sprint for debt, and never negotiate below 10% - below that line the tax exists on paper only.

Worked artifact: scored table

ITEM                                  SYSTEM      CoD  LEV  IDX  QUADRANT       SIZE  OWNER
Flaky CI suite (retries mask fails)   build        3    3    9   do now          M    Priya
Orders svc has no staging env         orders       3    2    6   this quarter    L    Marcus
Duplicated pricing logic (3 places)   billing      2    3    6   this quarter    M    Jen
Legacy cron with no alerting          reports      2    1    2   parking lot     S    -
Inconsistent lint config              all repos    1    1    1   parking lot     S    -

Read it: the CI suite scores 9 - it taxes every engineer every day (CoD 3) and every future change ships through it (LEV 3) - so it jumps ahead of the staging-env gap even though the staging gap caused the more memorable incident. That inversion of recency bias is the entire point of scoring.

Deliverable

Produce three artifacts: the scored inventory table (all items, both axes, index, quadrant), the quarter's funded list with t-shirt sizes and proposed owners, and a leadership proposal of no more than one page where every funded item is framed as cost/return, plus a parking lot with its 6-month expiry noted.

Do NOT

  • Do not filter the inventory before scoring - pre-filtering re-introduces the vibes the scoring exists to remove.
  • Do not use a finer scale than 1-3. A 1-10 scale invites false precision arguments about whether something is a 6 or a 7; the 2x2 only needs low/medium/high.
  • Do not pitch leadership on code quality, elegance, or "best practices" - pitch interest payments and unblocked roadmap.
  • Do not schedule low-CoD/high-leverage items standalone; fold them into adjacent feature work or they will lose every prioritization fight.
  • Do not let the parking lot skip its quarterly review; items older than 6 months get dropped or re-scored, not carried silently.
  • Do not put an XL item on the quarter plan un-decomposed.

Quality bar

  • Every inventory item traces to one of the three signal sources; guesses are labeled.
  • Every item has both axis scores, an index, and a quadrant - no unscored pet projects smuggled into "do now".
  • The funded list fits the team's realistic capacity after the debt-tax percentage is applied.
  • The proposal contains zero architecture jargon a non-engineer executive would need defined.
  • Owners are spread beyond the two most senior engineers.

Download now (ZIP)

Does it work?

Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.

No reviews yet

People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.

  • It worked
  • Partly
  • It didn't
What did you use it for? e.g. Reviewing pull requests in a Rails app

Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.

Your trail

Files you open will collect here, so you can find them again.

Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.

Now do this for your own.

Bring your CLAUDE.md, AGENTS.md or skills. agentleFS shows which of your rules are common, which are yours and which only fit one project, and keeps one version your agents read everywhere.