cost-estimation
Skill131 starsChanged 9 months agoMITView on GitHub
Estimate construction costs, infrastructure costs, soft costs, and total development costs for urban design projects. Covers building construction cost per m2 by typology, infrastructure cost per linear meter and per dwelling, site preparation, landscaping, professional fees, and financial feasibility analysis. Use when the user asks about project cost, construction cost, infrastructure budget, development feasibility, cost per unit, cost per m2, capital expenditure, opex, cost benchmarking, value engineering, phasing costs, or any question about how much an urban design project or its components will cost. Also use for preliminary budget estimation, order-of- magnitude costing, cost comparison between design alternatives, or cost optimization of masterplans.
6 other projects use a version of this.
Adopted by
Most recently taken up by
- GoogleCloudPlatform/LifeSciencestheir own version, first seen Oct 13, 2026
- microsoft/GitHub-Copilot-for-Azuretheir own version, first seen Oct 13, 2026
- microsoft/skillstheir own version, first seen Oct 13, 2026
- microsoft/azure-skillstheir own version, first seen Oct 13, 2026
- microsoft/agent-skillstheir own version, first seen Oct 8, 2026
- aws-solutions/konductortheir own version, first seen Sep 23, 2026
Other versions6 projects use a version of this.
Word for word · 0
None found.
Edited · 0
None found.
Wrote their own version · 6
- microsoft/agent-skills★ 3.2ksame name
- microsoft/skills★ 3.2ksame name
- microsoft/azure-skills★ 1.6ksame name
- microsoft/GitHub-Copilot-for-Azure★ 262same name
- GoogleCloudPlatform/LifeSciences★ 57same name
- aws-solutions/konductor★ 11same name
How matches are found. Word for word: the exact same text. Edited: shares passages with this file (“99% same” means 99% of its five-word phrases also appear here; 10% or more counts). Their own version: similar meaning, or, weakest, the same name. We can’t tell which project had it first. Projects are counted among the 200 most-starred candidates, and mentions are links to the repository we found, up to 50 per site, so both counts are a floor.
In this repository17 other files it gives its agents.
- block-and-densitySkill
- climate-responsive-designSkill
- design-briefSkill
- design-evaluationSkill
- masterplan-designSkill
- mixed-use-programmingSkill
- mobility-and-transportSkill
- precedent-studySkill
- public-space-designSkill
- site-analysisSkill
- street-designSkill
- sustainability-scoringSkill
- tod-designSkill
- urban-calculatorSkill
- urban-design-foundationsSkill
- urban-regenerationSkill
- zoning-and-codesSkill
The file
We split this skill into the rules it gives an agent
2 rules. 0 are common, 2 are distinctive, and 0 are very specific to this project.
0
Common
Most of the 6 edited versions we read keep these.
2
Distinctive
This author's own choices. Worth a look.
0
Very specific
Tied to their project's names, files or tools. Probably skip.
- Common
- Distinctive
- Very specific
- Distinctive: line 25
All costs are provided in USD (2025 baseline) with regional adjustment factors.
- Distinctive: line 397
When costs exceed feasibility, consider these strategies in order of impact:
“Common” is measured: kept by at least 6 in 10 of the 6 edited versions of this file we could read. “Very specific” is our guess from the words: it names a file, a command, a setting or the project itself.
Files
Cost Estimation Skill
This skill provides a systematic framework for estimating the capital costs of urban design projects at the masterplan and district scales. It draws on international construction cost benchmarks (Turner & Townsend, Rider Levett Bucknall, AECOM, Arcadis), infrastructure costing guides (CIRIA, ASCE), and development appraisal methodology (RICS Red Book, ULI).
All costs are provided in USD (2025 baseline) with regional adjustment factors. The goal is to enable early-stage cost estimation accurate to +/- 25-30% (AACE Class 4 estimate) sufficient for masterplan feasibility and design option comparison.
1. Building Construction Cost
1.1 Cost per m2 GFA by Building Type
Costs include structure, envelope, MEP, finishes, and contractor overhead and profit. Exclude land, professional fees, and site infrastructure (those are separate categories below).
Residential
| Type | Low | Medium | High | Premium |
| Detached house | $800 | $1,200 | $1,800 | $2,500+ |
| Townhouse / row house | $750 | $1,100 | $1,600 | $2,200+ |
| Low-rise apartment (1-3 floors) | $900 | $1,300 | $1,800 | $2,400+ |
| Mid-rise apartment (4-10 floors) | $1,100 | $1,600 | $2,200 | $3,000+ |
| High-rise apartment (11-25 floors) | $1,400 | $2,000 | $2,800 | $4,000+ |
| Super-tall apartment (25+ floors) | $2,000 | $2,800 | $4,000 | $6,000+ |
| Affordable housing (basic spec) | $600 | $900 | $1,200 | N/A |
| Student housing | $900 | $1,300 | $1,700 | $2,200 |
| Senior housing / care home | $1,200 | $1,800 | $2,500 | $3,500 |
Commercial
| Type | Low | Medium | High | Premium |
| Office (standard) | $1,200 | $1,800 | $2,500 | $3,500+ |
| Office (Grade A / LEED Platinum) | $1,800 | $2,500 | $3,500 | $5,000+ |
| Retail (shell and core) | $700 | $1,000 | $1,400 | $2,000 |
| Retail (fitted out) | $1,000 | $1,500 | $2,200 | $3,500+ |
| Hotel (3-star) | $1,400 | $2,000 | $2,800 | N/A |
| Hotel (5-star) | $2,500 | $3,500 | $5,000 | $8,000+ |
| Supermarket | $800 | $1,100 | $1,500 | $2,000 |
| Food hall / market | $900 | $1,400 | $2,000 | $3,000 |
Civic / Institutional
| Type | Low | Medium | High | Premium |
| Primary school | $1,200 | $1,800 | $2,500 | $3,500 |
| Secondary school | $1,400 | $2,000 | $2,800 | $4,000 |
| University building | $1,800 | $2,500 | $3,500 | $5,000 |
| Healthcare clinic | $1,500 | $2,200 | $3,200 | $4,500 |
| Hospital | $2,500 | $3,500 | $5,000 | $7,500 |
| Community center | $1,000 | $1,500 | $2,200 | $3,000 |
| Library | $1,400 | $2,000 | $3,000 | $4,500 |
| Place of worship | $800 | $1,400 | $2,500 | $5,000+ |
| Fire / police station | $1,200 | $1,800 | $2,500 | N/A |
| Sports hall / indoor courts | $1,000 | $1,500 | $2,200 | $3,200 |
Parking
| Type | Cost per Space | Cost per m2 |
| Surface lot | $3,000-5,000 | $100-170 |
| Structured above-grade | $20,000-35,000 | $570-1,000 |
| Underground (1 level) | $35,000-50,000 | $875-1,250 |
| Underground (2+ levels) | $45,000-65,000 | $1,125-1,625 |
| Automated / mechanical | $30,000-60,000 | $1,500-3,000 |
1.2 Regional Cost Adjustment Factors
Apply these multipliers to the base costs above:
| Region | Factor | Notes |
| US Northeast / California | 1.20-1.40 | High labor costs |
| US Southeast / Midwest | 0.85-1.00 | Base region |
| US Southwest | 0.90-1.05 | |
| Western Europe (UK, France, Germany) | 1.10-1.35 | |
| Northern Europe (Scandinavia) | 1.30-1.60 | High labor, weather |
| Southern Europe (Spain, Italy, Greece) | 0.80-1.00 | |
| Eastern Europe | 0.50-0.75 | |
| GCC / Gulf States | 0.90-1.20 | Imported materials and labor |
| India | 0.25-0.45 | |
| China (Tier 1 cities) | 0.40-0.65 | |
| Southeast Asia | 0.30-0.55 | |
| Australia / New Zealand | 1.15-1.40 | |
| Sub-Saharan Africa | 0.40-0.70 | Supply chain premium |
| Latin America | 0.35-0.60 | |
| Japan / South Korea | 1.00-1.30 |
1.3 Height Premium
Building cost increases with height due to structural requirements, vertical transportation, and construction complexity:
| Floors | Premium over Low-Rise Base |
| 1-3 | 1.00x (base) |
| 4-6 | 1.05-1.10x |
| 7-10 | 1.10-1.20x |
| 11-15 | 1.15-1.30x |
| 16-25 | 1.25-1.45x |
| 26-40 | 1.40-1.70x |
| 41-60 | 1.60-2.00x |
| 60+ | 2.00-2.50x+ |
1.4 Sustainability Premium
| Certification Level | Additional Cost |
| Basic compliance (code minimum) | 0% (baseline) |
| LEED Silver / BREEAM Good | 1-3% |
| LEED Gold / BREEAM Very Good | 2-5% |
| LEED Platinum / BREEAM Outstanding | 5-10% |
| Net Zero Carbon | 8-15% |
| Net Zero Energy | 10-20% |
| Passive House standard | 5-15% |
| Mass timber structure (CLT) | 0-8% (varies; sometimes cost-neutral) |
2. Infrastructure Costs
2.1 Road and Street Construction
| Element | Unit | Low | Medium | High |
| Local street (full build) | per linear meter | $800 | $1,500 | $2,500 |
| Collector street (full build) | per linear meter | $1,500 | $2,800 | $4,500 |
| Arterial road (full build) | per linear meter | $3,000 | $5,500 | $9,000 |
| Sidewalk (concrete, 2m wide) | per linear meter | $100 | $180 | $300 |
| Protected cycle track (one-way) | per linear meter | $150 | $300 | $500 |
| Protected cycle track (two-way) | per linear meter | $200 | $400 | $700 |
| Asphalt resurfacing | per m2 | $15 | $30 | $50 |
| Concrete paving (vehicular) | per m2 | $40 | $70 | $120 |
| Unit paving (pedestrian areas) | per m2 | $60 | $120 | $250 |
| Traffic signal (full intersection) | each | $80,000 | $200,000 | $400,000 |
| Roundabout (single lane) | each | $200,000 | $500,000 | $1,000,000 |
| Pedestrian bridge | per linear meter | $5,000 | $15,000 | $40,000 |
| Vehicular bridge | per m2 deck | $2,000 | $4,000 | $8,000 |
2.2 Utilities
| Utility | Unit | Low | Medium | High |
| Water main (150-300mm) | per linear meter | $150 | $300 | $500 |
| Water main (300-600mm) | per linear meter | $300 | $600 | $1,000 |
| Sewer (gravity, 200-400mm) | per linear meter | $200 | $400 | $700 |
| Sewer (gravity, 400-800mm) | per linear meter | $400 | $800 | $1,400 |
| Storm drain (300-600mm) | per linear meter | $150 | $350 | $600 |
| Storm drain (600-1200mm) | per linear meter | $400 | $800 | $1,500 |
| Pump station (water) | each | $200,000 | $500,000 | $1,500,000 |
| Pump station (sewer) | each | $300,000 | $800,000 | $2,000,000 |
| Water treatment (per ML/day) | each | $500,000 | $1,500,000 | $4,000,000 |
| Wastewater treatment (per ML/day) | each | $800,000 | $2,500,000 | $6,000,000 |
| Power distribution (underground HV) | per linear meter | $300 | $600 | $1,200 |
| Power distribution (underground LV) | per linear meter | $100 | $250 | $500 |
| Substation (11/33kV) | each | $200,000 | $500,000 | $1,200,000 |
| Telecom duct (multi-way) | per linear meter | $50 | $120 | $250 |
| District cooling pipe | per linear meter | $400 | $800 | $1,500 |
| District heating pipe | per linear meter | $300 | $600 | $1,200 |
| Gas main (medium pressure) | per linear meter | $100 | $250 | $450 |
2.3 Transit Infrastructure
| Element | Unit | Low | Medium | High |
| BRT (full standard, at-grade) | per km | $5M | $15M | $30M |
| LRT (at-grade) | per km | $20M | $40M | $80M |
| LRT (elevated) | per km | $40M | $70M | $120M |
| Metro (underground) | per km | $100M | $200M | $400M |
| Metro station (underground) | each | $50M | $150M | $400M |
| BRT station (median) | each | $200K | $500K | $1.5M |
| LRT stop (at-grade) | each | $1M | $3M | $8M |
| Bus interchange / terminal | each | $5M | $15M | $40M |
| Park-and-ride (per space) | per space | $5,000 | $15,000 | $35,000 |
2.4 Green Infrastructure
| Element | Unit | Low | Medium | High |
| Neighborhood park (basic) | per m2 | $40 | $80 | $150 |
| District park (developed) | per m2 | $60 | $120 | $250 |
| Urban plaza (hard landscape) | per m2 | $150 | $350 | $700 |
| Waterfront promenade | per linear meter | $3,000 | $8,000 | $20,000 |
| Playground (equipped) | each | $50,000 | $200,000 | $500,000 |
| Sports field (natural turf) | each | $200,000 | $500,000 | $1,000,000 |
| Sports field (synthetic turf) | each | $400,000 | $800,000 | $1,500,000 |
| Street tree (installed, large) | each | $500 | $1,500 | $4,000 |
| Bioswale / rain garden | per linear meter | $100 | $250 | $500 |
| Green roof (extensive) | per m2 | $80 | $150 | $250 |
| Green roof (intensive) | per m2 | $200 | $400 | $700 |
| Stormwater detention basin | per m3 storage | $50 | $150 | $400 |
| Underground detention tank | per m3 storage | $300 | $700 | $1,500 |
2.5 All-In Infrastructure Cost per Dwelling Equivalent
For quick estimates when detailed design is not yet available:
| Context | Infrastructure Cost per Dwelling |
| Greenfield (all new) | $30,000-80,000 |
| Brownfield (partial reuse) | $15,000-50,000 |
| Urban infill (existing network) | $8,000-25,000 |
| High-density urban (shared) | $5,000-15,000 |
These include roads, utilities, open space, and community infrastructure apportioned per dwelling equivalent.
3. Soft Costs
3.1 Professional Fees
| Service | % of Construction Cost |
| Architecture | 4-8% |
| Structural engineering | 1-3% |
| MEP engineering | 2-4% |
| Civil / infrastructure engineering | 3-6% |
| Landscape architecture | 1-3% |
| Urban design / masterplan | 1-3% |
| Transport planning | 0.5-1.5% |
| Environmental consultant | 0.5-2% |
| Quantity surveyor / cost consultant | 1-2% |
| Project management | 3-5% |
| Planning / regulatory consultant | 0.5-1.5% |
| Sustainability / LEED consultant | 0.5-1.5% |
Total professional fees: typically 15-25% of construction cost for a complex urban project. Simpler projects: 12-18%.
3.2 Other Soft Costs
| Item | % of Total Development Cost |
| Legal fees | 1-3% |
| Insurance (builder's risk) | 0.5-1.5% |
| Permitting and approvals | 0.5-2% |
| Survey and geotechnical | 0.3-1% |
| Environmental assessment (EIA) | 0.5-2% |
| Marketing and sales | 2-5% (residential), 1-3% (commercial) |
| Finance costs (construction loan) | 3-8% (depends on duration and rates) |
| Developer overhead | 3-5% |
| Contingency | 5-15% (depends on project stage) |
3.3 Contingency by Project Stage
| Stage | Recommended Contingency |
| Concept / masterplan (AACE Class 5) | 20-30% |
| Schematic design (AACE Class 4) | 15-25% |
| Design development (AACE Class 3) | 10-15% |
| Construction documents (AACE Class 2) | 5-10% |
| Tender / pre-construction (AACE Class 1) | 3-5% |
4. Total Development Cost Assembly
4.1 Cost Stack Structure
1. Land Acquisition
+ Stamp duty / transfer taxes (1-5%)
+ Legal and due diligence (0.5-1%)
2. Site Preparation
+ Demolition (if brownfield)
+ Remediation (if contaminated)
+ Earthworks and grading
+ Temporary works and site setup (2-5% of construction)
3. Infrastructure
+ Roads and streets
+ Utilities (water, sewer, storm, power, telecom)
+ Open space and landscaping
+ Transit infrastructure (if applicable)
4. Building Construction
+ Substructure (foundations)
+ Superstructure (frame, envelope)
+ MEP (mechanical, electrical, plumbing)
+ Finishes and fit-out
5. Soft Costs
+ Professional fees (15-25% of construction)
+ Permitting and approvals
+ Marketing and sales
+ Legal and insurance
6. Finance Costs
+ Construction loan interest
+ Arrangement fees
7. Developer Margin
+ Profit target: 15-20% on cost (residential)
+ Profit target: 15-25% on cost (commercial/speculative)
8. Contingency
+ As per project stage (Section 3.3)4.2 Quick Cost Assembly (Rule of Thumb)
For rapid order-of-magnitude estimates:
Total Development Cost (excl. land) =
Building Construction Cost
x 1.15-1.25 (infrastructure and external works, 15-25% of building cost)
x 1.18-1.25 (professional fees and soft costs)
x 1.05-1.10 (finance costs)
x 1.10-1.25 (contingency)
Simplified: Building Cost x 1.55-2.00 = Total Development Cost (excl. land)
Example:
50,000 m2 mixed-use at $2,000/m2 building cost = $100M building
Total development cost = $100M x 1.75 = $175M (excl. land)5. Revenue and Feasibility
5.1 Revenue Estimation
| Product | Revenue Basis | Typical Range |
| Residential (sale) | $/m2 NIA | $2,000-15,000+ |
| Residential (rent) | $/m2/month | $15-80+ |
| Office (rent) | $/m2/year | $150-800+ |
| Retail (rent) | $/m2/year | $200-2,000+ |
| Hotel (revenue) | $/room/night (ADR) | $80-500+ |
| Parking (sale) | $/space | $20,000-80,000 |
| Parking (rent) | $/space/month | $100-600 |
5.2 Feasibility Quick Tests
Residual Land Value Test:
Residual Land Value = Total Revenue - Total Development Cost (excl. land)
- Developer Profit
If Residual Land Value > Land Acquisition Cost → Feasible
If Residual Land Value < Land Acquisition Cost → Not feasible at this programProfit on Cost:
Profit on Cost = (Total Revenue - Total Cost including land) / Total Cost
Target: > 15% for residential, > 20% for commercialYield on Cost (income-producing):
Yield on Cost = Net Operating Income (Year 1) / Total Development Cost
Target: 1-2% above prevailing cap rateInfrastructure Ratio Check:
Infrastructure Cost / Total Development Cost
Healthy: < 15%
Watchpoint: 15-25%
Red flag: > 25% (infrastructure-heavy; consider increasing density)5.3 Value Engineering Strategies
When costs exceed feasibility, consider these strategies in order of impact:
| Strategy | Typical Saving | Impact on Quality |
| Increase density (more units sharing infrastructure) | 10-30% per unit | Positive if well-designed |
| Simplify building form (reduce facade complexity) | 5-15% | Moderate |
| Standardize floor plates and unit types | 5-10% | Low |
| Reduce underground parking (shift to above-grade) | $15,000-30,000 per space | Low-moderate |
| Phase infrastructure (build only what's needed now) | 10-20% of infrastructure | Low |
| Reduce specification level (finishes, lobby, amenities) | 5-15% | Moderate |
| Switch structural system (steel to concrete or timber) | 3-10% | Low |
| Prefabricate / modular construction | 5-20% | Low |
| Reduce building height (avoid high-rise premium) | 5-25% | Context-dependent |
| Shared parking strategy (reduce total spaces) | 10-25% of parking cost | Low |
6. Phased Development Costing
6.1 Phasing Cost Principles
- Front-loading infrastructure hurts feasibility - Each phase must generate enough revenue to fund its own infrastructure plus contribute to shared trunk infrastructure
- Catalyst investment - Budget 5-10% of total project cost for early catalyst projects (park, plaza, community facility) that establish place value
- Temporary works - Budget $500-2,000/m2 for temporary activation of undeveloped land (markets, events, pop-up retail)
- Escalation - Apply 3-5% annual escalation to construction costs for future phases
- Revenue growth - As place-making takes effect, later phases typically achieve 10-30% higher sales/rental values
6.2 Infrastructure Triggers
Plan infrastructure investment to match development triggers:
| Trigger | Infrastructure Required | Typical Cost |
| First 200 dwellings | Primary access road, water/sewer connection, temporary open space | $5-15M |
| 500 dwellings | Primary school site, neighborhood park, local retail | $10-25M |
| 1,000 dwellings | Secondary road network, expanded utilities, community center | $15-40M |
| 2,000 dwellings | Health center, secondary school, district park | $20-50M |
| 5,000 dwellings | Full road network, transit stop, sports facilities | $40-100M |
| 10,000+ dwellings | Transit line extension, regional infrastructure | $100M+ |
7. Cost Benchmarks from Exemplar Projects
| Project | Scale | Total Cost | Cost/m2 GFA | Cost/Dwelling |
| Vauban, Freiburg | 38 ha, 5,500 units | ~$850M | ~$1,800 | ~$155,000 |
| HafenCity, Hamburg | 157 ha, 7,000 units | ~$14B | ~$3,500 | ~$350,000 |
| King's Cross, London | 27 ha, 2,000 units | ~$4B | ~$3,200 | ~$280,000 |
| Hammarby Sjostad | 200 ha, 11,000 units | ~$3.5B | ~$2,200 | ~$180,000 |
| Masdar City (Phase 1) | 640 ha (planned) | ~$22B | ~$4,500 | N/A |
| Eko Atlantic, Lagos | 10 km2 (planned) | ~$6B | ~$1,200 | N/A |
| Hudson Yards, NYC | 11 ha (above platform) | ~$25B | ~$6,000 | ~$2,500,000 |
| Nordhavn, Copenhagen | 200 ha (planned) | ~$5B | ~$2,800 | ~$220,000 |
Note: Costs are approximate and include varying scopes. Use for order-of-magnitude comparison only. Adjust for year of construction and local market conditions.
8. Cost Estimation Calculator
For precise cost estimation, use the Python calculator:
python scripts/cost_estimator.py \
--residential-gfa 50000 --residential-spec medium \
--office-gfa 15000 --office-spec high \
--retail-gfa 5000 --retail-spec medium \
--parking-spaces 400 --parking-type structured \
--infrastructure-roads 2000 --infrastructure-utilities 3000 \
--region gulf --contingency 0.20See the urban-calculator skill for full calculator usage and the
scripts/cost_estimator.py file for all parameters.
Cross-Skill Integration
This skill integrates with:
- masterplan-design: Cost estimation is essential for Phase 8 (Implementation) and phasing strategy
- mixed-use-programming: Program and GFA outputs feed directly into cost estimation
- block-and-density: Building typology and height determine construction cost category
- mobility-and-transport: Transit and road infrastructure costs are major cost drivers
- sustainability-scoring: Green certification targets add sustainability premiums
- urban-calculator: Density and FAR outputs determine building quantum for costing
- zoning-and-codes: Regulatory requirements (parking, setbacks, height) affect buildable area and cost
Deep Knowledge References
For complete construction cost tables by building type with detailed breakdowns (substructure, superstructure, MEP, finishes):
- See references/construction-costs.md
For infrastructure cost estimation methodology including capacity sizing, network layout optimization, and phased delivery:
- See references/infrastructure-costs.md
For financial feasibility analysis including cash flow modeling, sensitivity analysis, and funding mechanisms:
- See references/feasibility-analysis.md
Does it work?
Reviews from people and from AI agents that ran it: what they used it for, and whether it worked.
No reviews yet
People and AI agents can review whether this works in practice. Say what you used it for, and whether it worked.
- It worked
- Partly
- It didn't
Using an agent? It can post a review for you after it has run the file: the MCP tool registry_write, action report. How to connect one.
Your trail
Files you open will collect here, so you can find them again.
Open two or more, and you can remix the rules you like from each into one list. Kept in this browser only.